We are approaching the final stages, the painter is already working and the tiler has started. Electricity is already installed throughout the house and RW/SW is laid over the 40 meters to the street. All other outstanding tasks are scheduled and the move-in is planned for early December. The driveway and the yard will also be finished in two weeks, the terrace has been done since last Saturday. Overall, we are at just about 8 months of construction time. Budget-wise, we are at around €2,500/sqm for KG300/400 including ground work. As of today, we will be below the cost estimate of the architect from March 23.