Hmm, no matter how I add it up, I somehow don't reach a total cost of €300,000...
- Additional construction costs 22,000
- Preparation of documents for building application 1,500
- Building application 1,000
- Soil survey 1,500
- Land registry office 2,000
- Construction electricity + construction water 1,000
- Connection costs 8,000
- Outdoor facilities 8,000
- Buffer 8,000
For me, the total is:
53,000
+ Land 100,000
+ House costs 170,000
= €323,000
Or have I just fundamentally misunderstood something in the list