Financing and house construction planning - is this okay? Experiences?

  • Erstellt am 2015-03-23 21:12:57

ypg

2015-03-23 22:57:05
  • #1
Just use the search function: Baunebenkosten :)
 

Lars881

2015-03-23 23:46:24
  • #2


In my opinion, they are obligated to do so, I've never heard otherwise. Once beforehand for the KfW application and again after completion for the final energy certificate. For the latter, it may be necessary to prove that the specified technology has actually been installed.
 

Schiffinho

2015-03-24 11:42:24
  • #3
Hmm, no matter how I add it up, I somehow don't reach a total cost of €300,000...

- Additional construction costs 22,000
- Preparation of documents for building application 1,500
- Building application 1,000
- Soil survey 1,500
- Land registry office 2,000
- Construction electricity + construction water 1,000
- Connection costs 8,000
- Outdoor facilities 8,000
- Buffer 8,000

For me, the total is:
53,000
+ Land 100,000
+ House costs 170,000
= €323,000

Or have I just fundamentally misunderstood something in the list
 

ypg

2015-03-24 14:24:53
  • #4
It's pretty accurate... Your list all belongs to the ancillary building costs (I overlooked that), so you have ancillary building costs of over €50,000, which should be more than enough and include a buffer. However, I think the house costs will be higher. Oh, with EL? okay... The outdoor area is material with EL, right?
 

Schiffinho

2015-03-25 11:28:57
  • #5
The proportions are about right, but no matter how I add up the list, I never reach the €300,000...
 

MichiQM

2015-03-25 18:27:15
  • #6
I find that already very cheap, 30k for all that. Are doors and windows included in the turnkey house?
 

Similar topics
20.07.2011House construction: Equity / incidental construction costs realistic?14
18.10.2012Ancillary construction costs and general expenses for a new semi-detached house14
18.06.2013Too few incidental construction costs or is the cost breakdown okay?16
05.02.2014Costs/planning land, additional construction costs, turnkey, etc.27
19.08.2014Home construction financing - House price and ancillary construction costs27
17.12.2014Building application "deferred". What does that mean?19
30.10.2015Can the building application be submitted this year?14
08.12.2016Financing KfW55 efficiency house, land and outdoor facilities19
01.02.2017Building application is becoming increasingly complicated!20
14.10.2018Building application - delay due to neighbor's lawsuit - experiences?21
17.12.2018What is set in stone in the building permit application?10
26.02.2019Submit a building application before the land is paid for?11
05.08.2020Building a garden shed... Is a building permit necessary? Detours?17
18.10.2020Baunebenkosten calculation realistic?94
13.10.2020Land available - ancillary construction costs, ancillary house costs, financing?34
10.12.2020Assessment of Additional Construction Costs - Have I considered everything?34
14.01.2021URGENT: Plausibility Check of Additional Construction Costs - 2 Days Before Deadline43
30.11.2021Fee notice for building application57
06.02.2022Are additional construction costs realistic? - 175m² living area KfW 5515
17.12.2024Is a house including ancillary construction costs feasible for 380K EUR?28

Oben