M.Dreising
2015-03-28 09:56:01
- #1
Oh how stupid, I must have made a mistake, then it is 23,000 euros for additional construction costs and only 7,000 euros buffer. Sorry that I explained it so complicatedly.
The base slab is included in the offer according to the construction company and we have not thought much about the earthworks yet, earthworks up to 30cm are included. The plot is located on farmland, will that be enough? Or what is your experience?
ypg: what do you mean by point 7 please? Thanks for the link - that is great!!! At the moment we don’t pay much rent and when the house construction starts we won’t pay anything anymore, because we live in the rental house of my parents-in-law and then we don’t have to pay anything for the last 6-8 months. (Thanks to the nice parents-in-law)
Planned is laminate at about 10 euros per 1sqm on 110sqm living area - 40-45sqm tiles (we have those done) that is 1100 euros just for the laminate itself and 900 euros for all accessories that belong to laying the laminate Is that not realistic?
The base slab is included in the offer according to the construction company and we have not thought much about the earthworks yet, earthworks up to 30cm are included. The plot is located on farmland, will that be enough? Or what is your experience?
ypg: what do you mean by point 7 please? Thanks for the link - that is great!!! At the moment we don’t pay much rent and when the house construction starts we won’t pay anything anymore, because we live in the rental house of my parents-in-law and then we don’t have to pay anything for the last 6-8 months. (Thanks to the nice parents-in-law)
Planned is laminate at about 10 euros per 1sqm on 110sqm living area - 40-45sqm tiles (we have those done) that is 1100 euros just for the laminate itself and 900 euros for all accessories that belong to laying the laminate Is that not realistic?