I recommend observing §12 paragraph 5 VOB/B
 

Tassimat

2019-11-24 11:19:58
  • #2
So the engineer caused the delay, not the construction company. Therefore, the construction company is not liable for damages. Now one would have to investigate the contracts with the engineer to what extent he was bound to deadlines etc. and whether there could be any liability for damages here. What financial damage have you demonstrably(!) suffered due to the delay?
 

guckuck2

2019-11-24 11:33:01
  • #3
That doesn’t matter, at least in relation to the construction company. That’s exactly why flat rates are agreed upon, so that not every euro has to be proven and disputed. Nevertheless, the responsible party must be clear. If the engineer had the scaffolding wrongly placed, that is more on his account. Besides the additional costs for the scaffolding, if there is no agreement, proof must then be provided as to whether any damage has occurred.
 

ypg

2019-11-24 11:44:42
  • #4
Weren't you present at the handover of the apartment yourself?
 

Hexe3000

2019-11-24 12:00:15
  • #5
No. The appointment was not disclosed to us despite our request. It only took place with the engineer we commissioned and the companies.
 

Hexe3000

2019-11-24 12:07:23
  • #6

I agree with that.
It just became clear to me that our engineering firm might be responsible. Then you cannot demand a contractual penalty from the roofing company. The possible additional costs, however, are damages. These would have to be claimed from the engineer. Of course, everything would have to be checked. In any case, now some of the engineer's statements as well as possibly the final invoice make sense to me.
Thank you very much for your support.
 

Similar topics
24.07.2013Additional costs due to underfloor heating11
15.03.2015Additional costs for dormer / gable or Frisian gable10
16.05.2016Scaffold closed - does this have consequences?11
03.12.2019Additional costs due to incorrectly planned ventilation system + floor-to-ceiling windows?50
27.11.2017Are additional costs for wood-look floor tiles normal?25
22.06.2018Unauthorized high-quality work - additional costs25
03.06.2018Liability issue regarding additional costs of a planning favor12
14.11.2019Construction contract additional costs foundation reinforcement?10
04.12.2019Are the additional costs for lime plaster instead of gypsum plaster realistic?16
18.04.2020Additional costs for sloped land with tree coverage42
30.05.2020Support hanging and filling - Additional costs?31
23.01.2021Laying tiles additional costs55
15.12.2020Has the professional association blocked the scaffold during self-performance?23
24.01.2021Additional costs for oak stair covering instead of beech – usury?16
21.05.2021Expired fixed price guarantee - additional costs29
09.07.2021First alleged fixed price and now additional costs - legal?79
29.03.2022Single-family house KfW55 - Extra costs: rip-off or justified?29
22.02.2023Soil report for bungalow 140 sqm, additional costs for WU concrete?33
05.03.2023Building in existing structures - Subsequent additional costs despite a fixed price57
12.09.2023Tile installation with additional costs for large format11

Oben