Evaluation of architect's cost statement for building completion

  • Erstellt am 2021-03-09 15:06:17

Kishihmen

2021-03-09 15:06:17
  • #1
Hello everyone,

we are currently building 3 terraced houses in the Stuttgart metropolitan area (3 builders). The construction is taking place through a general contractor on our own property. Unfortunately, the whole thing is not working as hoped and expected. At contract signing in February 2019, we were promised a move-in date of May/June 2020 (depending on the duration of the building permit/release). The actual start of construction was then in early July 2020. This would not basically be dramatic. BUT as of today, after almost 9 months, the basement is finished. The ground floor is also standing but shows serious defects (for details – there is also a thread here). In addition, we regularly learn from craftsmen that they have not been paid. Last week, we received information that the rent for the construction power box (contractual service of the general contractor) has also not yet been paid. The electrician then wanted to have the money from us (approx. €700) – after a conversation, the managing director of our general contractor told me that he currently does not have the money to pay for the construction power box. Insolvency has (not yet) been filed. We already had contact with a lawyer in February, who advised us against withdrawing from the contract as long as we do not have anyone who will continue the construction with us (at a financially feasible price). This brought us to look for alternatives. We now have a first offer from a former site manager of our general contractor, who is an architect himself. Personally, some of the values (e.g. completion of masonry) seem clearly too low to me, so I wanted to fall back on “crowd knowledge.”

Here are a few side infos about the planned buildings: Each terraced house has a basement, 2 full floors and a converted attic. The floor area is 10.5 x 6 meters. It is solid construction with unfilled Poroton bricks (36.5). Interior walls are also built of Poroton (11.5). Two bathrooms are planned (1st floor and attic), one of them with a bathtub, as well as a small guest toilet. Electrical: 130 sockets, electric roller shutters, no smart home. Heating: air-to-water heat pump with underfloor heating from the ground floor. Floors: bathrooms each with tiles, the rest vinyl.

I hope I was able to summarize all relevant information reasonably well. If not, feel free to ask.


































































































Construction site setup (construction fence, crane, construction staircase ...) 5,540.90
Completion of masonry (1st floor + attic) 11,454.39
Correction of masonry defects 15,000.00
Stonework 1,514.43
Carpenter, roofer 17,331.00
Plumber 1,899.05
Plastering work 18,533.00
Tiling work 11,322.18
Screed 4,471.18
Carpentry work 3,846.17
Roller shutter/shutter work 2,644.25
Windows/glazing 11,538.52
Painter/coating work 8,942.36
Floor covering work 4,230.79
Drywall work 1,009.62
Structural installations (stairs) 9,831.78
Sanitary installation 19,687.61
Heating installation 12,019.30
Electrical installation 18,004.90
TOTAL completion of building 178,821.43
Site manager activities 7,588.49
Project management 11,427.40
TOTAL coordination 19,015.89
GRAND TOTAL 197,837.32
 

11ant

2021-03-09 20:20:11
  • #2
I will hold back on construction cost calculation, but:

I see the risk that you are leaving out an essential item – namely your damages resulting from tolerating a delayed insolvency on the part of the general contractor. Assume that his (provisional) insolvency administrator will mercilessly collect from you everything the general contractor still has to receive from you – even if it is "only" lost profits, in case you resort to self-help when a ruin threatens due to lack of construction progress before weatherproofing is completed; and conversely, when accounting against each other, you will end up empty-handed. We are talking here about an amount of sunk money per house equivalent to a complete fitted kitchen or a carport – so the exterior facilities will almost certainly be completed two years later. Talk to your financiers about this additional requirement now – and in my opinion, best also about pooling together for the advance services of an insolvency procedure. The damage will only become greater if the administrator is called in too late. I believe I have already pointed out in the original thread about classic "born" third-party applicants (to whom discreet hints can be given).
 

Similar topics
07.09.2012Single-layer masonry vs. double-layer masonry with ETICS19
27.03.2014Interior walls upper floor lightweight construction instead of masonry?12
16.02.2016Question about contractual completion14
03.09.2016Buy the kitchen more than a year before completion?54
05.07.2016Exterior wall renovation basement14
08.08.2016Payment before or after completion of the construction phase?51
28.02.2017Are securities customary for completion and warranty?24
18.12.2017Offers for single-family house shell construction and basement received - your assessment?21
13.05.2018Two-layer masonry for residential basement on a slope - experiences?10
19.08.2018Strategically well-planned handover completion under building supervision11
18.10.2018Liability for various defects after acceptance of the property19
29.09.2020Building permit before completion of development31
28.12.2020House purchase with cracks in the basement20
22.01.2024Construction progress: Duplex with WU basement and developed attic813
09.06.2021House construction planning: solid house or prefabricated house? With or without a basement?80
14.11.2021Sell an apartment from a two-family house immediately after completion34
28.12.2022Floor plan single-family house city villa approx. 240m² without basement132
01.07.2022Construction delay without completion. The house simply is not finished21
19.04.2024Bank withdraws financing commitment due to defects20

Oben