Kishihmen
2021-03-09 15:06:17
- #1
Hello everyone,
we are currently building 3 terraced houses in the Stuttgart metropolitan area (3 builders). The construction is taking place through a general contractor on our own property. Unfortunately, the whole thing is not working as hoped and expected. At contract signing in February 2019, we were promised a move-in date of May/June 2020 (depending on the duration of the building permit/release). The actual start of construction was then in early July 2020. This would not basically be dramatic. BUT as of today, after almost 9 months, the basement is finished. The ground floor is also standing but shows serious defects (for details – there is also a thread here). In addition, we regularly learn from craftsmen that they have not been paid. Last week, we received information that the rent for the construction power box (contractual service of the general contractor) has also not yet been paid. The electrician then wanted to have the money from us (approx. €700) – after a conversation, the managing director of our general contractor told me that he currently does not have the money to pay for the construction power box. Insolvency has (not yet) been filed. We already had contact with a lawyer in February, who advised us against withdrawing from the contract as long as we do not have anyone who will continue the construction with us (at a financially feasible price). This brought us to look for alternatives. We now have a first offer from a former site manager of our general contractor, who is an architect himself. Personally, some of the values (e.g. completion of masonry) seem clearly too low to me, so I wanted to fall back on “crowd knowledge.”
Here are a few side infos about the planned buildings: Each terraced house has a basement, 2 full floors and a converted attic. The floor area is 10.5 x 6 meters. It is solid construction with unfilled Poroton bricks (36.5). Interior walls are also built of Poroton (11.5). Two bathrooms are planned (1st floor and attic), one of them with a bathtub, as well as a small guest toilet. Electrical: 130 sockets, electric roller shutters, no smart home. Heating: air-to-water heat pump with underfloor heating from the ground floor. Floors: bathrooms each with tiles, the rest vinyl.
I hope I was able to summarize all relevant information reasonably well. If not, feel free to ask.
we are currently building 3 terraced houses in the Stuttgart metropolitan area (3 builders). The construction is taking place through a general contractor on our own property. Unfortunately, the whole thing is not working as hoped and expected. At contract signing in February 2019, we were promised a move-in date of May/June 2020 (depending on the duration of the building permit/release). The actual start of construction was then in early July 2020. This would not basically be dramatic. BUT as of today, after almost 9 months, the basement is finished. The ground floor is also standing but shows serious defects (for details – there is also a thread here). In addition, we regularly learn from craftsmen that they have not been paid. Last week, we received information that the rent for the construction power box (contractual service of the general contractor) has also not yet been paid. The electrician then wanted to have the money from us (approx. €700) – after a conversation, the managing director of our general contractor told me that he currently does not have the money to pay for the construction power box. Insolvency has (not yet) been filed. We already had contact with a lawyer in February, who advised us against withdrawing from the contract as long as we do not have anyone who will continue the construction with us (at a financially feasible price). This brought us to look for alternatives. We now have a first offer from a former site manager of our general contractor, who is an architect himself. Personally, some of the values (e.g. completion of masonry) seem clearly too low to me, so I wanted to fall back on “crowd knowledge.”
Here are a few side infos about the planned buildings: Each terraced house has a basement, 2 full floors and a converted attic. The floor area is 10.5 x 6 meters. It is solid construction with unfilled Poroton bricks (36.5). Interior walls are also built of Poroton (11.5). Two bathrooms are planned (1st floor and attic), one of them with a bathtub, as well as a small guest toilet. Electrical: 130 sockets, electric roller shutters, no smart home. Heating: air-to-water heat pump with underfloor heating from the ground floor. Floors: bathrooms each with tiles, the rest vinyl.
I hope I was able to summarize all relevant information reasonably well. If not, feel free to ask.
Construction site setup (construction fence, crane, construction staircase ...) | 5,540.90 |
Completion of masonry (1st floor + attic) | 11,454.39 |
Correction of masonry defects | 15,000.00 |
Stonework | 1,514.43 |
Carpenter, roofer | 17,331.00 |
Plumber | 1,899.05 |
Plastering work | 18,533.00 |
Tiling work | 11,322.18 |
Screed | 4,471.18 |
Carpentry work | 3,846.17 |
Roller shutter/shutter work | 2,644.25 |
Windows/glazing | 11,538.52 |
Painter/coating work | 8,942.36 |
Floor covering work | 4,230.79 |
Drywall work | 1,009.62 |
Structural installations (stairs) | 9,831.78 |
Sanitary installation | 19,687.61 |
Heating installation | 12,019.30 |
Electrical installation | 18,004.90 |
TOTAL completion of building | 178,821.43 |
Site manager activities | 7,588.49 |
Project management | 11,427.40 |
TOTAL coordination | 19,015.89 |
GRAND TOTAL | 197,837.32 |