kutpic
2018-05-18 09:37:14
- #1
Hello,
we are currently planning to buy a plot of land that is still undeveloped. Sewer and water connections are located in the directly adjacent street.
I have now tried to determine the development costs based on the municipality's statute. This states for wastewater and water:
For undeveloped plots, one quarter of the plot area is taken as the floor area.
For wastewater:
The contribution is €1.50 per m² of plot area and €19.00 per m² of floor area.
For water:
The contribution is €1.50 per m² of plot area and €15.00 per m² of floor area.
For approximately 1000 m² I would therefore calculate
1000 * 1.50 = 1,500 * 2 = 3,000.00 €
+ 250 m² * 19 € = 4,750.00 €
+ 250 m² * 15 € = 3,750.00 €
totaling 11,500.00 €
Is this calculated correctly?
There is also a "Beitragssatzung für die Verbesserung und Erneuerung der Wasserversorgungseinrichtung" with €1.00 per m² of plot area and €10.00 per m² of floor area.
So another €3,500 if that also has to be paid.
So if I buy an undeveloped plot I would have to pay about €15,000 less than for a developed plot of the same size. Or am I completely mistaken? Unfortunately, I have no idea.
Addendum: although the total plot is 1500 m² of building area, about 1000 m² is [unentwickelt]. That is why I assume that development costs must be paid for 1,000 m². Is that correct?
we are currently planning to buy a plot of land that is still undeveloped. Sewer and water connections are located in the directly adjacent street.
I have now tried to determine the development costs based on the municipality's statute. This states for wastewater and water:
For undeveloped plots, one quarter of the plot area is taken as the floor area.
For wastewater:
The contribution is €1.50 per m² of plot area and €19.00 per m² of floor area.
For water:
The contribution is €1.50 per m² of plot area and €15.00 per m² of floor area.
For approximately 1000 m² I would therefore calculate
1000 * 1.50 = 1,500 * 2 = 3,000.00 €
+ 250 m² * 19 € = 4,750.00 €
+ 250 m² * 15 € = 3,750.00 €
totaling 11,500.00 €
Is this calculated correctly?
There is also a "Beitragssatzung für die Verbesserung und Erneuerung der Wasserversorgungseinrichtung" with €1.00 per m² of plot area and €10.00 per m² of floor area.
So another €3,500 if that also has to be paid.
So if I buy an undeveloped plot I would have to pay about €15,000 less than for a developed plot of the same size. Or am I completely mistaken? Unfortunately, I have no idea.
Addendum: although the total plot is 1500 m² of building area, about 1000 m² is [unentwickelt]. That is why I assume that development costs must be paid for 1,000 m². Is that correct?