Development costs - How are they calculated?

  • Erstellt am 2018-05-18 09:37:14

kutpic

2018-05-18 11:57:20
  • #1
Understood and yes, that makes sense. But can't that be calculated beforehand?

An even developed plot doesn't cost that much with us.

Do I have to pay for 1,500 sqm if only 950 sqm is allowed to be built on?

Does that mean that I would have had to pay the costs I calculated even for a developed property!?

Oh dear, I thought you could at least roughly calculate that.
 

montessalet

2018-05-18 12:06:42
  • #2
Yes, the costs also apply to a developed plot of land. The development costs are something different. There are many articles about this on the internet. Even with a developed plot, construction cost contributions and (house) connection costs are added. The construction cost contributions are usually due when submitting the building application. The construction cost contribution (mostly for wastewater) is very often calculated based on the plot area. And indeed on the entire.......
 

Zaba12

2018-05-18 12:06:57
  • #3


Just assume that your undeveloped plot + additional payment costs the same (for the same size) as the developed plot. But you should also consider the length of the adjoining road.

Do you know what I mean? If a 1000 sqm plot has 10 m of road and your 1000 sqm plot has 20 m of road, then in comparison you will probably have to pay more additionally.

In any case, you should know what additional payments you have to make before buying. Simply call the building authority and ask who can give you information about the amount of the additional payment.
 

kutpic

2018-05-18 13:12:42
  • #4
Ok, thanks for now! Then I need to ask the municipality more precisely.
By the way, I have already tried. The answer was that for an exact calculation there first needs to be a plan showing floor area, built-up plot area, etc.
But I'm not at that point yet. There is simply a standard land value for developed plots, so you know roughly what has to be paid for a building plot. If the seller agrees with that.
Regarding the mentioned plot, I have agreed with the seller that the development costs will be deducted from the purchase price, since he has not paid anything for the plot so far and does not have to pay more if I buy the plot. That's why I wanted to estimate the approximate amount. Since neither he nor I have any idea how high these costs are.
For developed plots, the owners have already had to contribute for years whenever there were improvements to the street, sewer, water facilities.
 

kutpic

2018-06-08 16:43:33
  • #5
Hello,
I have now inquired with the authority. My initial calculation with approximately 11,500 was correct. Additionally, there are costs for electricity and telephone connection. And a change in the statutes. Because currently, the property is not allowed to be developed.
Stupid situation for me now. I would like to secure the property, but I have no guarantee yet that I will be allowed to build on it.
The authority's statement is that I should wait until the statutes have been implemented and then submit a building plan. However, this can still take 3 to 4 months.
Then I only have the seller’s word, but I don’t know how much that is worth. Meanwhile, he can offer the property to others and thus drive up the price.
 

Similar topics
19.02.2015Development costs §127 Building Code12
02.07.2015Development costs for gas and sewer pipelines11
11.03.2018Backend development connection costs?30
22.05.2017Development costs are rising and rising13
30.01.2017Development costs and information before property viewing10
10.11.2017Back payment air heat pump disaster, contracting party, electricity supplier11
13.05.2018Development costs for subsequent construction10
21.09.2018Municipality development costs are too high - Should we commission it ourselves?16
19.10.2019Development costs / House connection costs11
15.01.2021Development costs for a plot in the second row35
29.03.2021150 Euro / sqm development costs = realistic or usury?58
03.04.2021Development costs are becoming increasingly expensive; can one resist?22
01.07.2022Building maintenance land in Hochwald/Hunsrück - Current development costs?10
14.08.2023Unclear clause in the development plan but authority does not answer questions23

Oben