Delays with the general contractor, no deadline set according to § 650 Building Code

  • Erstellt am 2021-04-07 20:59:24

rdwlnts

2021-04-08 20:48:25
  • #1
Well, it requires a sample selection, a workshop planning, then a scheduling appointment, a construction manager, a construction meeting of the client, construction manager, basement builder, earthworks contractor. Earthworks must also be done on the construction side.
 

ypg

2021-04-08 20:48:29
  • #2
Then start quickly. If you are responsible for the basement, then it’s your move, right?
 

rdwlnts

2021-04-08 20:49:29
  • #3
Take a look at Südwestkel***. Self-assignment of the cellar is standard.
 

Hausbau0815

2021-04-08 20:49:51
  • #4
Then it is not the general contractor's fault, but your own.
 

rdwlnts

2021-04-08 20:51:48
  • #5
Why? Selection first, then factory planning, then the rest. That belongs to the GC. After the preliminary planning and signing it, the GC needs about 5 months for the house. During that time, the pit is dug and the basement is built...
 

Hausbau0815

2021-04-08 20:57:09
  • #6

But you do know what "bauseits" means?
Bauseits means: Dthis service is not included in the offer but must be provided by someone else, without specifying exactly who this "someone else" is. That means that by adding "bauseits" in a contract, additional costs arise for the client.
 

Similar topics
28.01.2010House with or without a basement? - Experiences20
05.06.2010Basement made of high perforated bricks or concrete?11
18.08.2013Massive house with basement. Is our budget enough?11
08.12.2015Construction costs for KFW70 house with basement turnkey15
03.03.2012Position controlled residential ventilation in the underground basement?16
26.10.2012External perimeter insulation floor slab, basement mold risk11
09.06.2013Costs of earthworks without basement15
19.04.2013Budget for the construction of a single-family house with a WU concrete basement27
27.05.2013Cost estimation: prefabricated house, basement, carport, single garage10
01.07.2013Additional insulation in the Ytong basement (36 cm)14
27.07.2013Average construction time for a semi-detached house with a basement11
16.02.2014Floor plan of a single-family house with basement - Your opinions, please16
29.01.2014Cost saving/basement/affordable tiles/sealed screed?13
19.03.2014Cost for a new single-family house, 2 full floors, without basement18
05.07.2014Sleeping in the basement okay?14
13.08.2014Water intrusion in basement due to storm - insurance?17
03.02.2017Single-family house 2 floors without basement - floor plan - costs - feasibility?24
05.08.2014First offer, 157m2 with basement, KFW 70, garage14
30.09.2014New construction planning - single-family house 160 sqm without basement - floor plan, costs, etc..29
22.08.2022Floor plan of a single-family house just before final design - Please provide tips and advice93

Oben