OK. What is included in the amount of €8500? It can’t just be a few meters of construction road and hauling away the excavation. Is the digging included?
The €8500 net includes:
1. Creating the construction road: approx. 70-80 m² (estimated), 30 cm excavation + removal, compacting the base, filling with RC material 15 m³
2. Loading and removal of 55 m³ excavation. The digging is already included in the house price, unloading beside the house is free. So this is the extra charge for loading the truck, hauling away and disposal
3. Transporting and providing construction machinery for points 1+2
Individual prices:
1 x truck trip €130
1 m³ earth removal + disposal €56
Nothing else is included in the offer, also no price breakdown between the points