chrisw81
2019-07-12 13:58:06
- #1
The construction road was made by the shell construction company on the same day they started their work. About 80 m² of construction road, excavation about 20-30 cm (stored on the side, no disposal) and filled with RC. Costs about €1400. I thought that was okay and I was glad that the shell construction company did it at the same time and made the construction road according to their needs (driveway, crane, etc.). The excavated soil from this excavation and the excavation of the foundation slab (a total of about 60 m³) was stored on the side of the property, directly on the street. We then commissioned a separate disposal company, which was able to collect and transport the soil from the street 2-3 weeks later. Price about €2000.Hello, how did the matter turn out, if I may ask? We are currently facing a similar situation.