Cost breakdown of our house construction

  • Erstellt am 2017-02-19 09:21:44

ehaefner

2017-02-19 09:21:44
  • #1
I did some calculations and created a cost breakdown. I would appreciate it if you could tell me whether I have overlooked anything...

Land costs €65,000 (commission-free)

Notary and land registry ~ €2,000

Property transfer tax (3.5% here) €2,275

Surveying and batter boards ~ €2,000
Soil report ~ €550

Excavation and disposal (only foundation slab) realistically about €10,000?

Insurance €400

Signs / porta potty / construction electricity / construction water / container €1,500

House connection costs including meter box ~ €10,000? According to the municipality, water and telecommunications are connected; what does that mean for electricity? Are €10k then enough?

Measurement after moving in €600

Applications (building permit etc., including preparation by the construction company) €4,000

Buffer for road closure and co. €2,500

Foundation slab €15,000

House €275,000 (I am leaving out the detailed breakdown here, it is quite generously specified and includes additional insulation for KFW 40)

Carport and basic outdoor facilities €15,000

Have I forgotten anything or set anything too low/high? Thanks for reviewing!
 

RobsonMKK

2017-02-19 09:43:24
  • #2
Provider: either get prices from the homepage or call. Then you know what it costs.

Soil survey: do you already have an offer? We paid over 800

Carport and exterior for 15 might be tight. Carport can quickly also cost 5-7. Single or double?
 

ehaefner

2017-02-19 09:50:23
  • #3
I looked at the provider's website, but I can't make any sense of the technical jargon at all... And I don't know which amounts concern us... Outdoor facilities and carport are the only things where our own work is involved, my brother is building the carport (just material costs for us) and he will also do the landscaping and so on together with us... And since he is a forestry engineer at a tree nursery, we get it quite cheaply... That's why we have planned for 15k...
 

RobsonMKK

2017-02-19 10:01:22
  • #4
Then everything fits ;-) if only explanations follow comments, you don’t need them at all ;-)
 

ypg

2017-02-19 11:34:54
  • #5
Where is the rainwater being directed? Earthworks plus shaft can cost around 5000...
 

Nordlys

2017-02-19 11:52:49
  • #6
Is it a developed new development area? Then rainwater and sewage shafts may already be on the plots and included in the purchase price. Otherwise see above ypg. Container, exchange carport for precast concrete garage. The first to the countryside, also provides containers at the same time. Costs paid 14 days ago 7,800,- complete. Building permit. Paid 867,- in December. Connections. Sewage and rainwater with us 2,500,-, Telekom 800,-, electricity 900,-, drinking water 1,500,-. Additionally 1,500,- base fee to suppliers as construction cost allocation. Road closure, for what? In the new development area?
 

Similar topics
18.09.2012Construction of a base slab with frost skirt but without foundation10
09.09.2013Costs for soil replacement, soil survey for construction ground, clayey25
24.07.2014Soil assessment report, filling - additional costs?11
24.04.2018Massive double garage vs. prefab garage vs. carport46
10.08.2016Soil report - silty and artificial fill11
20.08.2016Base slab vs strip foundation15
16.11.2016Broadband supply for the new development area over my property17
27.03.2017Backfilling for foundation slab25
25.10.2017Costs for point foundations and carport drainage25
26.03.2018Is a soil report not possible before surveying the new construction area?16
26.02.2018Offer or calculation for a single-family house with wooden frame in order?11
15.05.2018Water, gas, and electricity - disconnection and reconnection?10
17.02.2019Dimensioning of house connection electricity/gas/water11
05.03.2020Carport with massive shed30
10.02.2021Run electricity from the house to the garage11
27.06.2020Base plate incorrectly positioned40
25.02.2021Pave the driveway, carport later - procedure?24
20.01.2022Placement of parking spaces / carport on the property42
15.02.2022Financing outdoor facilities, carport, equipment32
25.09.2023The supplier has incorrect meter numbers in the system - what to do?42