Construction stop by authority and demanded repair

  • Erstellt am 2021-04-01 01:26:17

hampshire

2021-04-04 16:59:13
  • #1
What would now be interesting to know is: What are the approval prospects for the necessary [Tektur]?
 

11ant

2021-04-04 21:31:41
  • #2
Feel free to explain that ;-)
 

ti.gris

2021-11-03 20:39:03
  • #3
Greetings all, we have finally overcome the hurdle with the [Landratsamt] and received our approval. Since our basement was now in an unfavorable condition for further activities, we created so-called defect reports to document the deficiencies and sent them to the general contractor. Instead of addressing these obvious defects, we were forbidden from entering the construction site. He justified this by stating that he is registered in the land register in the so-called first rank and that we therefore have no right to enter the construction site. Slowly, we just don’t understand the world anymore.
 

K1300S

2021-11-03 21:01:58
  • #4
??? I don't understand. If he is a general contractor, he has no rights to your property at all. Or is he really a property developer this time?
 

ti.gris

2021-11-03 21:48:05
  • #5
There are a total of two companies, one is the so-called planning office and is registered first in the land registry until the house is completed. The other company is responsible for the construction of the building. Since both are related to each other, there is a certain connection. Our defect reports have always been addressed to the company responsible for the construction. But responses (below the belt) have always been received from the planning office. Together, these two act as a general contractor / property developer. I think the problem is that we are only registered second in the land register.
 

Oetzberger

2021-11-03 22:05:34
  • #6
Sounds like an unhealthy mix of the disadvantages of a developer construction model with the risks of building on your own land using a general contractor. You should discuss all steps with a lawyer; you will hardly get any help here in the forum.
 

Similar topics
23.03.2011Developer or architect?15
25.03.2012Land now - house construction next year23
03.08.2012Contract Supplement to the Construction Contract by the Developer36
14.01.2014Buy land let build dream house26
23.06.2014Developer charges heavily for replanning - justified?12
02.07.2014Realistic purchase of land and new construction of a single-family house & how to finance it?20
08.10.2014How do you search for a suitable property developer?30
06.01.2015First buy the plot, then calmly plan and build...?11
27.02.2015Construction project with a developer without an official building plan, is a down payment required?12
07.05.2015Have the work contract checked by a professional37
02.12.2016Plots in Cologne only through developers?54
05.09.2017Developer or general contractor! Safety?30
17.10.2017Property developer or independent architect26
17.11.2019General contractor in the Munich area or prefabricated house?37
06.01.2020House purchase, prefabricated house from the developer with land10
16.05.2021Approach for Initial Contact with Property Developers & Prefabricated Building Suppliers24
16.03.2022Additional construction costs when building a house with a developer88
25.02.2023Property purchased 05/22, can we withdraw from the purchase?22
25.05.2023Plot Single-family house New development area60
18.11.2024Land promotional houses experiences?34

Oben