Comigo99
2021-10-26 14:22:02
- #1
Good day dear community,
currently we have the following problem:
we are currently building in BaWü and are already in the shell construction phase - however, the invoice for the civil engineering work is still outstanding.
An acquaintance from my hometown (you could almost call him a buddy) did all the civil engineering work for my house with a basement (he is the junior manager of a large civil engineering company that usually only does major construction sites). At the beginning, we also got a great price here (friendship price), which made us about 3-4k cheaper than other civil engineering companies for the same service.
At the beginning, he sent us all the necessary information and offers and was really committed. Afterwards, he practically handed over the construction site to his site manager, whom I also knew from my hobby "football" (he actually played in the same team for 1 year). That was okay for us and he really did a great job - you could say: we were really satisfied.
Everything went great! The problems that arose a few weeks ago (landslide) were also excellently handled and professionally refilled and the slope was properly secured.
After about 2 weeks everything was done and the work areas were to be refilled:
On a Friday evening, the site manager's representative (the site manager was unfortunately on vacation) was supposed to come by for a meeting with the general contractor on site. During the appointment he called and said he couldn't come... So we discussed everything further over the phone together with the general contractor and the shell builder. It was said all the time: "For him everything is clear what should happen."
So far so good...
Then on Tuesday (after no one had simply come on Monday even though it was agreed... but well... that's how it is on construction sites - we're used to it xD) we arrived at the construction site:
The driveway + terrace (south-west terrace around the corner) was gravelled (as agreed) and the additional west side (here the slope had slid, creating an extremely wide work area) was ALSO COMPLETELY gravelled. Meaning: significantly more gravel + significantly more excavation material that had to be hauled away + excavation material that still remains on our property and should have been in the hole instead.
To not go too far into detail: additional costs of about €2,000 - €2,500 net + excavation material that still somehow needs to be hauled away (disposal and transport costs of certainly another €1,000 - even if you get it somewhere "cheap").
So if I add everything up, we definitely have additional expenses of around €3,000 WITHOUT having wanted it that way!
The site manager also apologized for this and largely admitted the mistake, but nevertheless tried to find excuses such as: "We couldn’t get to the excavation material (tight construction site) and therefore had to fill with gravel" --> For me that's rubbish... Crane, excavator... all there! These would also have been things that could have been discussed on the said Friday. Unfortunately, no one from the civil engineering company was there and so they just dumped the gravel and finished.
Problem No.2: At the beginning we were told that one combined inspection shaft was included but he would recommend installing 2 shafts (due to various advantages...). We therefore decided on 2 shafts - but specifically asked if that would be cost-neutral. He then clearly said: "No, that doesn’t cost anything extra." So we decided on 2 shafts even though we didn’t want that for aesthetic reasons at first.
Now in the invoice: 2x inspection shafts at €1,500 each --> in the original offer obviously only 1 shaft at €1,500 - so simply charged double... - sure: 2 shafts = double price?? For us it was definitely agreed differently back then!
Effectively, one can say that we have additional costs of about €4,500 that are totally unnecessary and were not agreed upon that way.
The fact is: everything has obviously been installed - the "test invoice" as my buddy calls it is in our possession. Next week we will meet to discuss the invoice, but I fear that he will not simply say: "Our fault, we deduct €5,000 and that’s it."
How would you proceed in this case? What would you agree to, or what compromise should one find here?
According to the offer and the service specifications at the time and also according to the agreements by e-mail etc. back then, nowhere was it even remotely mentioned that almost all areas should be filled with gravel! It was also said that this would be discussed again on site... Like I said, that did not happen --> lack of communication
The same with the shaft... in the offer and in the service specification it was always one shaft - he installed 2 but of course charged double.
currently we have the following problem:
we are currently building in BaWü and are already in the shell construction phase - however, the invoice for the civil engineering work is still outstanding.
An acquaintance from my hometown (you could almost call him a buddy) did all the civil engineering work for my house with a basement (he is the junior manager of a large civil engineering company that usually only does major construction sites). At the beginning, we also got a great price here (friendship price), which made us about 3-4k cheaper than other civil engineering companies for the same service.
At the beginning, he sent us all the necessary information and offers and was really committed. Afterwards, he practically handed over the construction site to his site manager, whom I also knew from my hobby "football" (he actually played in the same team for 1 year). That was okay for us and he really did a great job - you could say: we were really satisfied.
Everything went great! The problems that arose a few weeks ago (landslide) were also excellently handled and professionally refilled and the slope was properly secured.
After about 2 weeks everything was done and the work areas were to be refilled:
On a Friday evening, the site manager's representative (the site manager was unfortunately on vacation) was supposed to come by for a meeting with the general contractor on site. During the appointment he called and said he couldn't come... So we discussed everything further over the phone together with the general contractor and the shell builder. It was said all the time: "For him everything is clear what should happen."
So far so good...
Then on Tuesday (after no one had simply come on Monday even though it was agreed... but well... that's how it is on construction sites - we're used to it xD) we arrived at the construction site:
The driveway + terrace (south-west terrace around the corner) was gravelled (as agreed) and the additional west side (here the slope had slid, creating an extremely wide work area) was ALSO COMPLETELY gravelled. Meaning: significantly more gravel + significantly more excavation material that had to be hauled away + excavation material that still remains on our property and should have been in the hole instead.
To not go too far into detail: additional costs of about €2,000 - €2,500 net + excavation material that still somehow needs to be hauled away (disposal and transport costs of certainly another €1,000 - even if you get it somewhere "cheap").
So if I add everything up, we definitely have additional expenses of around €3,000 WITHOUT having wanted it that way!
The site manager also apologized for this and largely admitted the mistake, but nevertheless tried to find excuses such as: "We couldn’t get to the excavation material (tight construction site) and therefore had to fill with gravel" --> For me that's rubbish... Crane, excavator... all there! These would also have been things that could have been discussed on the said Friday. Unfortunately, no one from the civil engineering company was there and so they just dumped the gravel and finished.
Problem No.2: At the beginning we were told that one combined inspection shaft was included but he would recommend installing 2 shafts (due to various advantages...). We therefore decided on 2 shafts - but specifically asked if that would be cost-neutral. He then clearly said: "No, that doesn’t cost anything extra." So we decided on 2 shafts even though we didn’t want that for aesthetic reasons at first.
Now in the invoice: 2x inspection shafts at €1,500 each --> in the original offer obviously only 1 shaft at €1,500 - so simply charged double... - sure: 2 shafts = double price?? For us it was definitely agreed differently back then!
Effectively, one can say that we have additional costs of about €4,500 that are totally unnecessary and were not agreed upon that way.
The fact is: everything has obviously been installed - the "test invoice" as my buddy calls it is in our possession. Next week we will meet to discuss the invoice, but I fear that he will not simply say: "Our fault, we deduct €5,000 and that’s it."
How would you proceed in this case? What would you agree to, or what compromise should one find here?
According to the offer and the service specifications at the time and also according to the agreements by e-mail etc. back then, nowhere was it even remotely mentioned that almost all areas should be filled with gravel! It was also said that this would be discussed again on site... Like I said, that did not happen --> lack of communication
The same with the shaft... in the offer and in the service specification it was always one shaft - he installed 2 but of course charged double.