torsan
2016-04-11 20:45:16
- #1
Hi,
I had 10K€ to burn, but then came
- Extra charge for stairs (white ash instead of beech, 2K€)
- Bathroom (>5K€)
- Tiles were more expensive
- Busch Jäger doorbell with video and remote access
- 66 LED recessed spotlights plus dimmer (all in the distribution) >2K€
- Electrical... Wow, that hit hard. Home automation, sockets, etc.
- I totally forgot the satellite dish!
- Kitchen, painter, flooring, earth removal, paving work – all more expensive than planned and than the cost estimate. At some point I started adding 10% on top of the estimate.
In the end, about 30K€ extra must have been spent. Without the garden.
Cheers, torsan
I had 10K€ to burn, but then came
- Extra charge for stairs (white ash instead of beech, 2K€)
- Bathroom (>5K€)
- Tiles were more expensive
- Busch Jäger doorbell with video and remote access
- 66 LED recessed spotlights plus dimmer (all in the distribution) >2K€
- Electrical... Wow, that hit hard. Home automation, sockets, etc.
- I totally forgot the satellite dish!
- Kitchen, painter, flooring, earth removal, paving work – all more expensive than planned and than the cost estimate. At some point I started adding 10% on top of the estimate.
In the end, about 30K€ extra must have been spent. Without the garden.
Cheers, torsan