Tx-25
2020-05-13 20:21:27
- #1
Hello. Our installer delivered a different boiler than originally planned. His reasoning is that otherwise the BAFA subsidy would not be met. The small boiler above in the niche was also added as a result.
Unfortunately, the boiler no longer fits in the niche. However, this niche was not originally intended for the heating system anyway. The connections on the boiler are at the back. The boiler is exactly as wide as the niche. So, the plumber cannot secure the pipes first and then place the boiler into the niche. The pipes also cannot pass alongside the boiler because both are the same width.
What can we do? Aren't there flexible connections that can be screwed on first and then the boiler pushed halfway into the niche? Do you have any other ideas? The plumber suggests the spot where it is currently standing.

Unfortunately, the boiler no longer fits in the niche. However, this niche was not originally intended for the heating system anyway. The connections on the boiler are at the back. The boiler is exactly as wide as the niche. So, the plumber cannot secure the pipes first and then place the boiler into the niche. The pipes also cannot pass alongside the boiler because both are the same width.
What can we do? Aren't there flexible connections that can be screwed on first and then the boiler pushed halfway into the niche? Do you have any other ideas? The plumber suggests the spot where it is currently standing.