Wood price increase - order confirmation already signed

  • Erstellt am 2021-04-13 07:46:17

lisa-kessler

2021-04-13 07:46:17
  • #1
Hello dear forum members,

we already signed the order confirmation for our house in August 2020.

In October this year we will sign the work contract and in November the foundation slab will be made.
Around May the earthworks will start.

The house erection is next year in April.

Now we have heard about the massive price increases in the wood sector.

Can we expect a price increase despite the signed OC?

Wording OC: "House: March/April 2022, depending on the weather conditions and completion of the preparatory work.

The final construction sum will be recorded in the work contract after completion of the approval planning and sampling in the factory.

In case of financing refusal by the credit institutions, the order confirmation expires without any costs."
 

MM1506zzzz

2021-04-13 08:18:06
  • #2
What exactly does the contract (why order confirmation ??) that you signed say? Since the house price apparently has not yet been finalized:




If I were you, I would expect an increase. The home building company still has plenty of room to price this in.
 

lisa-kessler

2021-04-13 08:21:43
  • #3


Hello MM1506zzzz,

the order confirmation lists the type of construction, the construction site, and all costs. The house manufacturer wanted the order confirmation so that he has security and can firmly schedule the date. The total costs are stated in it, except for those of the sample selection and other things that we would decide on afterward.
 

guckuck2

2021-04-13 08:23:54
  • #4
Then get ready for interesting prices at the reorganization.
 

lisa-kessler

2021-04-13 08:24:49
  • #5


So basically, that he then includes the increased lumber prices in there?

What legal value does such an order confirmation have? The prices are fixed in it, we also signed it that way.
 

lisa-kessler

2021-04-13 08:27:24
  • #6
But everything is really transparent... We have already seen all the things that are included in the [Standard]. So at the sample selection there should be no nasty surprises for us.
 

Similar topics
28.04.2014Cost estimate - contract for work16
07.05.2015Have the work contract checked by a professional37
06.07.2015Termination of work contract for house construction (before construction)14
06.12.2016Contract for work before property purchase - real estate acquisition tax?10
16.02.2016Question about contractual completion14
22.02.2016Signature of the work contract before financing?15
03.09.2016Buy the kitchen more than a year before completion?54
04.07.2016Purchase of property under a work contract12
19.07.2016When did you sign the work contract? Prior planning?12
08.08.2016Payment before or after completion of the construction phase?51
28.02.2017Are securities customary for completion and warranty?24
08.08.2018Withdrawal from the work contract within the withdrawal period23
19.08.2018Strategically well-planned handover completion under building supervision11
26.09.2019ScanHaus Work Contract Additional Agreement14
27.01.2020How do I get out of a contract for work?11
11.02.2020Withdrawal from the work contract (The shell construction simply does not start)33
07.05.2022Work contract with exclusion §14/1522
01.07.2023Provision interest and deadlines of the house building company in the work contract13
06.08.2023Work contract individual or lump sum?11
21.09.2023Installer installs wrong heating system, offer vs order confirmation13

Oben