Yaso2.0
2021-06-09 11:00:34
- #1
could we also contact the GU before the vacation and ask if anything might come up in the next few weeks that we need to react to quickly.
I just called the GU.
The earthworks are supposed to start in week 25 and then the base slab will follow. The masons are scheduled to be with us in week 33. By then we will already be back.
The GU says: Nothing else will happen after the base slab. It will rather be delayed than go faster.
The base slab will be inspected by our expert. I also called the expert and asked what he thinks of our idea. He also said that we can/should still do it now instead of coming up with the idea to want to travel in autumn.
Since we will be traveling by car, I will book us a hotel with cancellation option. If it does turn out that we have to stay, then we will cancel it, but at least we can go, if the mentioned schedule holds.
Thanks for your opinions!