hondazp11
2018-06-11 00:11:13
- #1
Hello,
after we have already been annoyed several times by the working methods of our construction manager, there was the next disaster over the weekend.
Our heating system was installed.
Unfortunately, its dimensions do not match those of the planning. As a result, the heating unit now not only partially covers the window, but it also cannot be fully opened.
According to the plan, the heating system is positioned so that there is enough space at the window.
The construction manager created the planning and the tender and presented it to us for signature; we commissioned the heating system.
Now it turns out that it does not fit.
The construction manager refers to the fact that his drawing is only schematic.
Enough to be upset about.
To what extent there is a planning error here has yet to be clarified.
Do you have to accept something like this? The actual dimensions differ from those in the plan.
My main question now is, if we have to deal with all this as it is, then we need to carry out damage limitation:
The heating system is positioned angled in the back right corner in front of the window with a distance of about 70 cm to the outer wall. Next to the heating system towards the window, an expansion vessel and a filling station for the outdoor module are installed.
If these were relocated to another location, one could, if at all possible, turn the heating unit and place it directly against the outer wall. (There would theoretically be enough space. The heating system is 70 cm wide, the space is 80 cm.
Is this even possible? Can these two elements, the expansion vessel and the filling station, be relocated?
Thank you in advance for your advice.
Regards, Franzi
after we have already been annoyed several times by the working methods of our construction manager, there was the next disaster over the weekend.
Our heating system was installed.
Unfortunately, its dimensions do not match those of the planning. As a result, the heating unit now not only partially covers the window, but it also cannot be fully opened.
According to the plan, the heating system is positioned so that there is enough space at the window.
The construction manager created the planning and the tender and presented it to us for signature; we commissioned the heating system.
Now it turns out that it does not fit.
The construction manager refers to the fact that his drawing is only schematic.
Enough to be upset about.
To what extent there is a planning error here has yet to be clarified.
Do you have to accept something like this? The actual dimensions differ from those in the plan.
My main question now is, if we have to deal with all this as it is, then we need to carry out damage limitation:
The heating system is positioned angled in the back right corner in front of the window with a distance of about 70 cm to the outer wall. Next to the heating system towards the window, an expansion vessel and a filling station for the outdoor module are installed.
If these were relocated to another location, one could, if at all possible, turn the heating unit and place it directly against the outer wall. (There would theoretically be enough space. The heating system is 70 cm wide, the space is 80 cm.
Is this even possible? Can these two elements, the expansion vessel and the filling station, be relocated?
Thank you in advance for your advice.
Regards, Franzi