RE-1407
2025-05-02 15:03:12
- #1
We installed a terrace measuring 4x10 meters 4 years ago with 1x1 meter ceramic tiles, 2cm thick, laid in concrete; nothing has moved to this day. It will probably not move for the next several decades either. Our second terrace, about 15 sqm at the same house, was laid according to the same pattern. I have experienced that I prefer to spend money once rather than twice. Depending on how the base was prepared and possibly “shifts,” there can be nasty surprises! How big is the difference? For us, 5 years ago, the labor costs were 270 €/sqm (concrete) and 160 €/sqm (gravel) plus the cost of the tiles.