Termination of work contract - processing fee "without prejudice"

  • Erstellt am 2024-12-11 09:34:20

MiKoRLPWinch

2024-12-11 09:34:20
  • #1
Hello everyone,

we want to build a house in RLP, the following is stated in the contract for work:

1. The client can terminate the contract if the contractor has exceeded the construction period with the completion of the house (for your information: 12 months plus bad weather) and is in default. Before termination, the contractor must be given a written grace period. This amounts to at least 4 weeks. The possibility of termination in the event of an unsuccessful expiry of the grace period must be pointed out.

OK - understood.

But
2. If the client terminates the contract without the termination being caused or justified by the conduct of the contractor, the contractor is no longer bound to the lump sum price. He can invoice his services according to his list prices. Notwithstanding this, the contractor may, in the event of termination of the contract by the client or in the event of withdrawal from the contract claim a processing fee of up to 5% of the agreed gross contract price including chargeable special requests without proof of damage. No claim for lost profits.

Does this mean that even if I as the client terminate the contract for the aforementioned reasons (e.g. non-compliance with the construction period, unsuccessful grace period), the contractor is still allowed to charge this processing fee?
Or only if the termination is not justified?

The word "notwithstanding" unsettles me here.

Thanks a lot in advance.
 

nordanney

2024-12-11 10:02:29
  • #2
That is the crux. Exceeding the agreed construction period + grace period = caused by the contractor's behavior Point 2 only applies to unscheduled terminations (just terminated like that). Not legal advice, lay opinion. Legal advice only possible from a lawyer.
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18
06.09.2024Contractual penalty in the Building Code contract - new construction20

Oben