Silent approval procedure

  • Erstellt am 2015-03-30 23:37:01

sch1014

2015-03-30 23:37:01
  • #1
Hello, we submitted a building inquiry for a small hall with a horse stable (garage in the front, stable in the back, on the outskirts) to the district administration about five months ago. Twelve weeks ago, during a personal visit, we were informed that the inquiry was approved so far and that we would receive mail in the next few days. When no mail arrived after eight weeks, we went there again. Now there would be problems with the horse keeping. After discussions, the caseworker said he would talk to his boss again and that we would receive mail in the next few days. This was already 14 days ago. My question: I heard something about a silent approval procedure if the authority does not respond within three months. Can someone give me information about whether this is the case? And what should I do next?
 

Bauexperte

2015-03-31 01:35:01
  • #2
Good evening,

I have not heard the term "stilles Genehmigungsverfahren"; I also can't find anything about it online. Therefore, I think you are confusing something here and mean the "vereinfachtes Genehmigungsverfahren." This must—if all required documents have been submitted—also be decided within one month in RLP.

For a building preliminary inquiry, I find no information regarding deadlines to be observed in RLP—comparable to NRW. This means in my opinion that it depends on the responsible caseworker when you receive mail.

It is different with a regular building application; here, there are indeed deadlines to be observed.

Rhenish regards
 

DG

2015-03-31 10:09:39
  • #3
With the "silent approval procedure" it is presumably meant that the building permit is considered granted if the formal building application is not answered by the authority within a deadline. However, this does not work with a preliminary building inquiry.

Best regards
Dirk Grafe
 

Similar topics
02.01.2012Semi-detached house - who submits the building application first, wins?29
14.02.2013Long waiting time - building permit deadline18
29.10.2013Property reserved, construction financing plan, architect/building permit application21
30.01.2014Preliminary building inquiry before purchasing property okay, can this information be trusted?15
05.10.2014Approval procedure for moving a house15
17.12.2014Building application "deferred". What does that mean?19
17.06.2016Further procedure in case of rejection of the preliminary building inquiry35
16.07.2016Purchase Agreement for Land - Building Window - Preliminary Building Inquiry12
22.02.2017Building inquiry - What is relevant?12
22.09.2017Telephone construction inquiry rejected13
11.05.2018Construction application costs only 40 euros due to exemption application?27
14.08.2019Building inquiry / Letter to the District Office12
26.11.2021Preliminary building inquiry, sale of partial plots, procedure21
09.05.2022Building application due to parking spaces not approved. What can happen?30
13.03.2023Preliminary construction inquiry for land purchase: What should be considered?24
10.03.2023Preliminary building approval positive, building application criticized position29
14.08.2023Unclear clause in the development plan but authority does not answer questions23
20.03.2024Submit a building inquiry in Hamburg16
15.04.2024Is the involvement of the nature conservation authority necessary for a preliminary building inquiry?14
30.06.2024Should the building inquiry with exemption be rejected?11

Oben