Share of trades in % of the total construction cost

  • Erstellt am 2017-09-19 22:28:55

Lumpi_LE

2017-09-20 16:34:04
  • #1
The shell is often around 40%. Of course, this varies, but it's a point of reference. You are at about 45%. Tendentially, you thus have a higher-quality shell compared to the internal standard, or, with the now experienced KfW70 house, a lower internal standard.
 

_Nerz_

2017-09-21 07:15:35
  • #2
Ok thanks, the thing is that in the turnkey offer I am only given the total construction cost and not the individual prices for the trades. Due to the lack of transparency, I only requested an offer for the shell construction.
 

11ant

2017-09-21 12:47:04
  • #3
That’s not a bug, I would say, it’s a feature. A package offer is not meant to educate the customer about the calculation, but rather to be cheaper as a whole than all its parts. You can buy a Golf complete, which is a great idea for its purpose. Or you go around the corner, not through the big door to the car dealer, but through the side entrance to the parts seller. Then you ask again what the Golf costs in individual parts: six figures! It’s similar with the builder, and there is nothing wrong with that in itself. Want very special sports rims? – then order the car with winter tires. That also works with the house: change the construction service description to bare lightbulbs hanging from the ceiling and then get the great designer lights from Ingvar Kamprad yourself. You can get separate quotes for each trade. But what will regularly happen to you is that another provider will charge only 95 % of the price, which initially sounds 5 % cheaper – but the general contractor will only give a 92 % discount if you want to leave it out. And then in the end it becomes 3 % more expensive. Packages, after all. That’s not the case for all items; in total you manage to save peanuts. And for those you get several contacts for complaints. Is that really a gain?
 

Joedreck

2017-09-21 13:10:06
  • #4
That's right, that's the rule. However, there are also other GCs who offer a kind of modular system. From shell construction to all other trades are also offered individually. Very fair and transparent
 

11ant

2017-09-21 13:19:58
  • #5
Certainly, but the main point is that the package discount increases with the scope of the package. Such a thing usually only becomes worthwhile if the brother-in-law is a heating engineer. Removing small trades is rather hardly worthwhile.
 

_Nerz_

2017-09-23 21:10:52
  • #6
Planning 240 m2 for ground floor, upper floor and basement. Have been offered a price of 700 euros per m2 for the shell construction. Included in the price are also a concrete stair landing, chimney, cistern with 3500 liters, structural engineering and architectural supervision. No roof is included.

What do you think? Is it too expensive or a fair price?
 

Similar topics
14.11.2011Shell construction still this year15
05.09.2015Cracks in masonry (shell construction)14
13.02.2014Mold on wood/ shell construction, is it possible to deduct the advance payment invoice?28
24.04.2015Buy tiles during shell construction24
09.03.2015Received an offer from a builder: Cost of shell construction - experiences?26
27.02.2015Purchase shell construction and complete it including financing15
11.02.2016Cost per cubic meter of built-up shell space14
07.05.2016Buying a shell construction - Experiences21
03.10.2016Single-family house, hillside location, basement half residential/useful area - expensive shell construction?15
20.04.2017Payment plan with 35% after the shell construction, okay?10
05.05.2017Rough construction flat-rate offer - forgotten necessary items11
06.09.2017Add a wind catch later to the shell construction17
07.10.2017From when must the shell construction be dry or sealed?16
18.12.2017Offers for single-family house shell construction and basement received - your assessment?21
31.01.2022Possible savings in self-performed structural work37
27.08.2018New building shell construction selection: Choose a company or architects?52
18.09.2018No offer for electrical work - must the shell construction be stopped?12
09.10.2018Costs for shell construction and roof covering/insulation - fixed price offer okay?25
09.01.2019Final invoice for shell construction (200 sqm, clinker, without basement, roof) ok?24
26.06.2019Shell construction offer - what do you think?10

Oben