Sealing the single-unit house entrance

  • Erstellt am 2019-02-14 10:36:23

readytorumble

2019-02-15 10:29:42
  • #1
Wow, €1500 for an element that is probably bought there for under €200. Installing a multi-utility connection takes at most 1 hour. We were forced by the electricity provider to install a multi-utility connection (cost €600 and we did it ourselves). At first, I was annoyed about it, but afterwards, I’m glad and it was definitely the safest and also a cheap and simple solution. So if the single entries are only slightly cheaper, I would choose the multi-utility option in your place.
 

chrisw81

2019-02-15 11:00:11
  • #2
Let's assume I take the multi-utility. What about wastewater then? Multi-utility would be for us electricity, drinking water, gas, telecom. Wastewater is discharged from the house at 2 points. What about the protective conduit here? The problem remains despite multi-utility...
 

Obstlerbaum

2019-02-16 16:57:02
  • #3
Our energy supplier charges nearly 2000 euros for the construction of the MSH including civil engineering work and the laying of several empty conduits.
 

chrisw81

2019-02-18 09:10:10
  • #4
I always thought it was the construction company's job to provide and install the MSH... but interesting. We are doing everything privately on our property because the endpoints are already all on the property.
 

Similar topics
17.04.2016Value of land and bungalow B5511
08.11.2010Offer for a semi-detached house with land, okay?11
07.07.2011Financing land now, house in 6 months?17
14.08.2012Build a home? Land in prospect19
25.03.2012Land now - house construction next year23
31.05.2012Financing of the property: Does the entire financing need to be secured?11
04.09.2012Land paid - Building with an additional loan?16
02.09.2013Angular bungalow on 800m² plot - financially feasible?16
09.02.2013What do you think of this property?11
05.04.2015Property reserved. Financing is pending52
13.03.2018Turnkey Construction Land and Prices79
16.12.2015Sewage costs - I am somewhat stunned15
31.07.2019Filling and compacting the ground for the house155
31.07.2018House connection costs for wastewater. Included in the ancillary construction costs with 3.5K.13
15.05.2019Are the house connections already one meter on the property?16
30.09.2019Floor plan optimization of a single-family house with a basement on a small plot178
15.01.2021Development costs for a plot in the second row35
05.06.2021New building connection costs, especially wastewater17
10.08.2022Fiber optic connection is being installed - use existing multi-utility infrastructure?30
12.02.2025Suitable slope for wastewater14

Oben