Hello,
we are slowly entering the final phase. The building application has been approved, the plot has been paid for, detailed plans are currently being created, and the house and tile sampling is done. Only the bathroom planning and sanitary sampling at the wholesaler are still missing.
What bothers me about our general contractor is the poor communication regarding the process under the motto "When do I do/apply for what". I suspect that something is being deliberately delayed here, since the company is building at least 9 houses in the newly developed building area. It is not a very small company, but at the same time building 9 houses seems like a lot to me.
Maybe we are just too fast and the information would have come later anyway. We would like to complete the sampling now, as the baby is expected next month. However, this was difficult especially with the sanitary sampling, as the planning and sampling takes place at the wholesaler and we can only get prices through a sanitary specialist company. But the specialist company has not yet been decided. How can detailed plans be created if, for example, the water/sewage routing changes again due to the bathroom planning?
The next issue is construction electricity/construction water. The application deadline for the building applications was recently extended until mid-August; we did not yet own the plot because the building area was not yet completed. Everything looked like construction would only be able to start in September. Suddenly, it went quite fast. The building application has now been approved, the plot has been completed and could be paid for, etc. All requirements for the start of construction have thus been created. According to the contract, the construction company now has 1 month until construction begins. In my opinion, construction electricity and water are needed as soon as possible. But again, no information like "You urgently need to... if we want to start in July."
What are your experiences regarding this? Did you have a checklist or a schedule to orient yourselves in terms of timing? When did you do the sanitary sampling?
Regards
we are slowly entering the final phase. The building application has been approved, the plot has been paid for, detailed plans are currently being created, and the house and tile sampling is done. Only the bathroom planning and sanitary sampling at the wholesaler are still missing.
What bothers me about our general contractor is the poor communication regarding the process under the motto "When do I do/apply for what". I suspect that something is being deliberately delayed here, since the company is building at least 9 houses in the newly developed building area. It is not a very small company, but at the same time building 9 houses seems like a lot to me.
Maybe we are just too fast and the information would have come later anyway. We would like to complete the sampling now, as the baby is expected next month. However, this was difficult especially with the sanitary sampling, as the planning and sampling takes place at the wholesaler and we can only get prices through a sanitary specialist company. But the specialist company has not yet been decided. How can detailed plans be created if, for example, the water/sewage routing changes again due to the bathroom planning?
The next issue is construction electricity/construction water. The application deadline for the building applications was recently extended until mid-August; we did not yet own the plot because the building area was not yet completed. Everything looked like construction would only be able to start in September. Suddenly, it went quite fast. The building application has now been approved, the plot has been completed and could be paid for, etc. All requirements for the start of construction have thus been created. According to the contract, the construction company now has 1 month until construction begins. In my opinion, construction electricity and water are needed as soon as possible. But again, no information like "You urgently need to... if we want to start in July."
What are your experiences regarding this? Did you have a checklist or a schedule to orient yourselves in terms of timing? When did you do the sanitary sampling?