Reservation of land / Construction company inquiry / Supplier - Bank

  • Erstellt am 2014-02-14 20:25:46

Grym

2014-02-14 20:25:46
  • #1
Hello,

I would like to know in which order one should carry out which steps!?

The plot of land can presumably be reserved from May
Development during the course of the year
Start of construction 2015 (or maybe only 2016)

To go to the bank, I need a fairly precise picture of what costs will be incurred, right?
The main parts are:
- Land costs and incidental acquisition costs: Fairly precisely plannable as soon as the plot can be reserved, I assume
- Construction costs: For this, I probably need a contract ready for signature with a builder, right?
- Development costs: For this, I need offers from the gas supplier, electricity supplier, water supplier, etc. – when can one request these!?
- Additional construction costs: If I deduct the incidental acquisition costs of the land and all development costs, only small amounts should arise here
- Floor coverings/painting work: We will do this ourselves – so we have to go to the DIY store and see what we will buy
- Outdoor facilities: Here one should probably also get an offer!? Primarily this concerns paving the access path and terrace – there will certainly be prices per square meter
- Basement: We should also have offers made for this
- Reserve for extras

But, when can I get offers from construction companies? As soon as the plot is reserved but not yet developed? As soon as reserved and developed? Only after purchase? Or can I already get offers without the plot? Basically "from the top edge" – do companies go along with this, or do they only want to "invest time" shortly before it becomes concrete? How far in advance can one inquire with construction companies?

When can I inquire about gas, electricity, water, sewage, etc.? It’s not about "having it done," I just want an offer from the companies stating that development up to the basement costs such and such. Can the documents from the development company be sufficient or does the development have to be completed by the developer so that the gas/electricity/water companies can make their offers?

When can I inquire with basement construction companies?
 

ypg

2014-02-15 00:55:39
  • #2
About the topic of developers: they have fixed amounts that belong to additional construction costs. So you can ask about them already now.
Additional construction costs: never plan below 30,000... if it’s too much, you will use it at the latest for the sanitary/electrical upgrades.
Own work painter: plan here a multiple... we bought the paint at the specialty store, but also used a multiple at the hardware store for tools and consumables.

Construction costs/Additional construction costs

To give construction-interested people an idea of the costs smart people calculate, clueless people have to reckon with:

Additional construction costs:

    [*]Notary land contract.......................453 €
    [*]Site plans................................................183 €
    [*]Notary mortgage deed.......................454 €
    [*]Tax office real estate transfer tax......3037 €
    [*]District court land registry entry........104 €
    [*]District court land register................1025 €
    [*]Soil survey...............................................655 €
    [*]Building permit........................................634 €
    [*]Water supply association...................1926 €
    [*]Electrician construction power box.........388 €
    [*]Installer water meter/construction water..257 €
    [*]Provision interest KFW124.......................8 €
    [*]Association of private builders...................90 €
    [*]Update foundation according to report....3800 €
    [*]House surveying......................................584 €
    [*]Earthworks (45cm topsoil etc.)...............3053 €
    [*]Provision interest KfW124....................124 €
    [*]approx. 100 m3 topsoil removal...........1800 €
    [*]Construction power, installment payment....100 €
    [*]Expert building inspection.......................370 €
    [*]Provision interest....................................260 €
    [*]Construction water, installment payment....390 €
    [*]Provision interest....................................180 €
    [*]Rental dehumidifier, 2 weeks...................230 €
    [*]Rainwater and sewage shaft...................3000 €
    [*]Gas connection.........................................1500 €
    [*]Civil engineer, connections........................510 €
    [*]Supplementary permit, garage..................90 €
    [*]Power supplier.........................................1140 €
    [*]Rainwater drainage and courtyard gravel..3300 €
    [*]Garage, HT pipes rainwater......................65 €
    [*]Telekom...................................................400 €
    [*]Edging of the forecourt
    [*]Paving
    [*]House entrance platform
    [*]House border

We might be “surprised” by further costs; the list is only the current state of affairs.
Your costs can of course be completely different.
Interior upgrades (gross prices, surcharges on construction service descriptions, dependent on craftsmen):

    [*]Garage: sectional door in anthracite........1250 €
    [*]Window opening in the storage room.............65 €
    [*]2nd frost-proof outdoor faucet..................370 €
    [*]Drywall, special services.......................1000 €
    [*]Pre-wall installations bathroom..................1200 €
    [*]Bathtub, 180 x 80 + installation...............1000 €
    [*]Heating platform........................................110 €
    [*]One built-in spotlight including installation....40 €
    [*]Built-in radio including installation...............200 €
    [*]One socket................................................28 €
    [*]SAT dish including installation.......................650 €
    [*]Toilet without flush rim.................................120 €
    [*]Shower thermostat......................................220 €
    [*]Shower channel + installation........................560 € Oh dear :-(
    [*]Installation washbasin countertop..................50 €


Wow, a window in a Zapf garage would cost 441 €! Rip-off!!!

For personal reasons, I will not disclose all our items here.
Feel free to ask me some questions by email.

Miscellaneous:

    [*]Topping-out ceremony....................................500 €
    [*]Green manure................................................25 €
    [*]Pickaxe............................................................20 €
    [*]Household insurance for storage.....................30 €
    [*]Ladder (for chimney sweep)............................80 €
    [*]Wheelbarrow...................................................75 €
    [*]Cable drum (always needed)............................70 €
    [*]Fan heater.......................................................40 €
    [*]Drill bit for ETICS..........................................15 €
    [*]Industrial vacuum cleaner, rental/day................20 €
    [*]Moving company, storage................................1200 €
    [*]Moving company............................................1400 €
    [*]Various tips
    [*]Fuel costs or a new car

Purchases that are (not always) necessary:

    [*]Mailbox........................................................120 €
    [*]House number (incl. ancillary costs)................43 €
    [*]Utility room cabinets (Ikea).................................600 €
    [*]2 outdoor lights, up/down...............................100 €
    [*]Indoor lights of choice, from 50 €/piece per living area
    [*]Indoor lights of choice, from 20 €/piece per secondary room
    [*]Light bulbs (LED approx. 10 € each)
    [*]Platforms for washing machine + dryer................160 €
    [*]Bathroom mirror.............................................300 €

Material costs of own work:

    [*]Floor coverings of choice
    [*]Carpet adhesive, primer, filler for screed, baseboards, etc., plan about 1/4 of the carpet area (parquet adhesive is much more expensive!)
    [*]Various special dowels (basic equipment upon moving in)..................50 €
    [*]Painter’s paint, specialty store + tools............1200 €
    [*]Hardware store: paint, consumables....................600 €
    [*]Washbasin, bathroom.......................................50 € creative skills required!
    [*]Washbasin supports..........................................100 €
    [*]Wall cladding + working materials..................400 €


Keep in mind that you have to buy a lot of tools if you want to do it yourself.
You should calculate several sets for multiple helpers (we needed many things twice—for two people), painter’s rollers about a dozen.
You should also not be stingy; it usually leads to duplicate purchases anyway.
Nevertheless, you save several thousand euros in craftsman hours.

For exterior facilities, you have to take a fixed price, it always turns out differently...

Have several companies provide calculations for a specific construction project that best corresponds to your wishes (sqm, technology).
That way you can calculate for the bank.
 

Similar topics
20.07.2011House construction: Equity / incidental construction costs realistic?14
02.09.2013Angular bungalow on 800m² plot - financially feasible?16
18.10.2012Ancillary construction costs and general expenses for a new semi-detached house14
27.06.2013Construction costs rough estimate, realistic or not?42
02.08.2013Construction cost estimate for our dream house12
05.02.2014Costs/planning land, additional construction costs, turnkey, etc.27
09.04.2014Questions/neglected plot/meadow, determining construction measures44
13.03.2014Additional construction costs and realistic additional construction costs?21
11.10.2022List of incidental construction costs. More expensive "on the builder's side"?154
21.04.2015Is a floor plan with a garage feasible on the property?29
02.07.2015Development costs for gas and sewer pipelines11
15.08.2016Property - Building window - Location of house and garage44
20.12.2023Placement of house and garage on plot12
07.08.2017Construction costs approx. 400K - Is financing construction feasible this way?11
10.02.2020Place house, garage / carport on the property93
19.10.2019Development costs / House connection costs11
13.10.2020Land available - ancillary construction costs, ancillary house costs, financing?34
20.10.2021Alignment of house and garage on the property18
29.06.2023Position of garage on property, specification in development plan22
26.03.2025Orientation of single-family house + garage on west-east plot with street on the west18

Oben