Realistic building financing? Your opinions

  • Erstellt am 2015-01-15 16:01:45

michisa86888

2015-01-15 16:01:45
  • #1
Hello, we are currently at the beginning of planning our own home. I am 28 years old and my girlfriend is 26 years old. We have a monthly income of €3300. Equity is around €50000. Our goal is not to exceed total costs of €350000. We want to build a single-family house with a basement, 1.5 stories, with about 140-150 sqm of living space + pitched roof. The plot will cost around €70000. Now my calculation: €350000 minus €35000 ancillary construction costs minus €70000 plot. That leaves €245000 for the house. Do you see that as realistic and feasible? We definitely want children later, so we would also have to consider that.
 

nordanney

2015-01-15 16:05:27
  • #2
House will probably fit, with a basement it will be more than tight :(
 

Doc.Schnaggls

2015-01-15 16:11:00
  • #3
A basement will probably not be enough, I agree with nordanney.

What is completely missing in the list, however, is a buffer for unforeseen expenses.

You should also consider at least 10 - 15 TEUR for that!
 

michisa86888

2015-01-15 16:24:06
  • #4
Thanks first of all for your answers.
I'm primarily interested in rough numbers for what everything will cost. A buffer is irrelevant for now, since the shell construction, earthworks, and most of the interior finishing, as well as planning, will be done by myself.
There will still be plenty deducted financially from that ;)
What do you think, roughly how much will the house with a basement cost? It should be of medium to upper standard.
 

f-pNo

2015-01-15 17:02:39
  • #5


On the one hand - I see it similar to Doc and nordanney - a basement will be difficult with this sum.
The price depends on the type of use and finishing (utility basement or living basement).
I seem to remember that for a living basement around 30,000 EUR are due (correct me if I'm wrong). But it can also get more expensive quickly if your plot conditions require a "white tank" (waterproof basement).

I wouldn't take the matter of the buffer too lightly. Especially since you aim for a mid to upper standard. Many construction companies set limits - e.g. tiles up to 30 euros. If these cost more (upscale equipment), several thousand euros can quickly disappear unplanned.

Regarding the own work, the following should be noted:
You only save the "personnel costs" (manpower). Materials still have to be paid for.
Also, you have to see if you can manage a lot of own work in terms of time and physical effort. Especially if you are "not a professional," you can easily misjudge this. In addition, the people doing the own work must be free every weekend/evening/etc. and motivated to spend a few hours on the construction site – over weeks/months.

Two examples:
- We did the painting work ourselves. My father (older generation) has a lot of experience in painting. Myself, my wife, and my mother (as far as she could help) I would rather call rookies (with a bit of experience). Still, I was convinced that we would finish everything in 2 – at most 3 weeks. Well – the preparatory work alone took almost a week. In the end, it was a good 4 weeks (rather 5), during which we didn’t take it easy (there in the morning, back late in the evening, famous cut sandwiches for lunch).
After the phase of own work, my father looked really bad. We were seriously worried about letting him drive home alone (600 km). On the second to last day, we took the house key away from him so he could finally take some rest.

- Initially, we planned to do part of the interior finishing ourselves. Gypsum boards were to be installed on the ceiling of our upper floor. Luckily, we gave up on this plan. How were two of us (father and I as laymen) supposed to screw a 2.5 m x 1.5 m gypsum board overhead?

Last but not least:
If you are still tenants and carry out "time-consuming own work," you still pay interest on your loan. This double burden must be borne. The longer the own work takes, the longer the financial double burden lasts. Here one should consider whether it might be sensible to outsource a trade (and thus finish quickly) or do it yourself. Also – if your own work takes longer than planned, you might hold up other trades that cannot continue = additional delay.
 

michisa86888

2015-01-15 17:13:37
  • #6
Wow that is quite an answer :-)
Regarding own contribution and time, we are fully aware. We are professionals, my 2 brothers and I are bricklayers and I am additionally a construction technician. There will be no competence problems.
It is supposed to become a utility basement, possibly with a granny flat.
We have no double burden as we have moved back to our parents' house to save money.
 

Similar topics
02.02.2012Own contributions? What is feasible?13
03.06.2013Buying land from father - building a house yes or no?11
12.02.2014Transfer property to son, contractually exclude daughter10
21.04.2015Terraced house - Financial framework, land + construction financing13
05.11.2016Plan for building a single-family house, sticking point living basement, dream or nightmare41
08.08.2016Idea not feasible due to residential basement?17
18.11.2016Small plot - does it suit us?11
16.08.2017Plan self-performed work seriously13
14.01.2018Own contributions / ancillary construction costs in new construction15
15.04.2019Residential basement approx. 80 sqm, how expensive?22
06.08.2020€420,000 budget for a house including land in northern Brandenburg23
13.06.2022Should the land be filled up or not?87
01.02.2021Single-family house 159 sqm - Straight plot - Correctly calculated?26
18.02.2021Plot on the northern slope – next steps?25
08.06.2021Single-family house planning on a slope (2,700 sqm plot) - Experiences / Discussion42
21.04.2022Basement living versus more living space on the ground floor64
18.02.2023Floor plan - plot for a single-family house, slight slope approx. 175m²67
01.10.2024Is the plot suitable for a narrow house for 5 people?43
30.01.2025Rough construction cost estimate single-family house13

Oben