Sure, but:

-Reversal of the burden of proof after tacit acceptance
-The warranty period begins after tacit acceptance and not after defect remediation

The legal consequences can be drastic.
 

oggear51

2017-01-16 16:18:17
  • #2
So the architect has long known about every defect except the missing hydraulic balancing, which I only noticed recently, but nothing has happened so far; the final invoice is still outstanding with the heating engineer and the window manufacturer, so there has also been no acceptance. I will send the architect one last defect rectification notice. If nothing happens, no one will get any money, quite simple.
 

Benextra

2017-01-16 22:41:23
  • #3
...Oggear, are you registered in the land register? Because that is usually what the BT / GU use for blackmail. Before the final invoice, there is the completion notification and invitation to acceptance by the builder. But everything is too vague here, I don't know the contract. I rejected the acceptance due to significant defects and after multiple requests for defect rectification, I had a lawsuit filed based on the protocol. But I am already living in it. Then go to a specialist lawyer for construction law...
 

oggear51

2017-01-17 12:10:11
  • #4
do you mean entered in the land register before construction begins?
 

Benextra

2017-01-17 20:23:31
  • #5
...no, I am the entry in the land register as the owner - after the priority notice of conveyance.
 

Similar topics
19.07.2018Draw the plan yourself? Do you necessarily need an architect?11
18.02.2011Architect totally messed up - experiences?17
30.09.2012Final invoice architect13
27.10.2013Architect --> Agreements? What is that?21
16.04.2014Cost of soil survey - Does the architect pay or do we?12
24.04.2014The remaining amount will not be paid out because the land register has not been released19
16.09.2014Termination of collaboration with architect - demands excessive fee28
01.10.2014Collaboration with an architect - how does it work properly?22
25.02.2015Planning / Architect, involvement of specialist planners for the approval plan10
11.06.2015Triple entry in the land register27
23.09.2016Owner/land register for a couple not yet married28
14.03.2017Property purchase, should the spouse be registered in the land register?17
31.05.2017Inspection of the land register parents' house21
13.08.2019Hereditary leasehold land, land register - take over outstanding debt?15
08.09.2019Type of use in the land register. Holiday home rentable or not?23
25.10.2019Gift / Semi-detached house / Land register23
07.01.2021Building a house for 2 brothers, how to proceed (division, measuring, land registry, etc.)?21
21.03.2021Land registry later than planned - save KfW funding18
29.07.2022Inheritance semi-detached house - Will or land register decisive?47
05.11.2022Old easement in the land register13