Hello,

I would like to buy an apartment in a new development project of a multi-family house. Two buildings with 11 apartments each (70-100 sqm) are being constructed.

I am now interested in how the rough process of such a construction looks like and what time frame can be expected.

The shell is already standing, windows and interior walls were installed before Christmas.

It looks like the interior plastering is now beginning (in front of the first of the two buildings there is such a tank). The buildings are heated with two large heating units.

Can you roughly estimate how long the rest of the construction will take until a possible move-in? And what are the upcoming construction phases?

Thank you very much.
 

11ant

2018-01-12 19:20:17
  • #2
There is no typical general procedure. If the investor has several irons in the fire and sales go faster at another project, work will also be scheduled more quickly there. Materials and labor are prioritized where they can be turned into sold residential units the fastest. Your own signature is like a turbo button – and you know when you press it long before we do.
 

dapfr

2018-01-12 19:39:56
  • #3
That makes sense. I would still be interested in an average value. And above all, also the typical process, just out of curiosity, because I would like to learn more about it.
 

tomtom79

2018-01-12 22:53:06
  • #4
Windows and shell construction finished, with a house it would still take at least 4-6 months.
 

11ant

2018-01-13 01:07:53
  • #5

As said, there is no such thing.

And neither does that exist.

Here you can read dozens of times how fast it went with this or that small house builder – for individual single-family houses, as well as for single-family houses from developers, or for condominiums.
But there is no typical or average value for eleven-family houses, who would even record that specific statistic?

From a seven-family house in my neighboring town I can tell you, from the finished shell to windows installed eight months, and two more until the external thermal insulation composite system (ETICS) was all around. But that is in no way representative or transferable, so what use is it to you now? – do you think you will get a hundred answers here to determine the average value yourself?

Trying to extrapolate from single-family houses would be comparing apple pie to stewed pears.
 

toxicmolotof

2018-01-13 01:51:24
  • #6


Well, what else will come? Everything that is stated in the contract but has not yet been installed.

My crystal ball tells me: forecast 3 months to 3 years.

What do you want to know that for? What date is specified in the contract?

Ask the site manager to tell you when it will still take 3 months. Then you have a rough orientation for the termination of the apartment.
 

Similar topics
25.10.2008Is laundry drying prohibited in the new apartment?!10
14.11.2011Shell construction still this year15
13.02.2014Mold on wood/ shell construction, is it possible to deduct the advance payment invoice?28
27.05.2015Huge problem with condensation on the window34
27.02.2015Purchase shell construction and complete it including financing15
07.05.2016Buying a shell construction - Experiences21
30.06.2016Is forced release of roller shutters on a window mandatory?41
03.10.2016Single-family house, hillside location, basement half residential/useful area - expensive shell construction?15
27.02.2018Too high humidity in the apartment. 60-70% in winter33
10.08.2018Installation of floor-to-ceiling window & French balcony, old building, 4th floor12
11.08.2019Installing raffstores in the shell construction prepared for blinds15
27.10.2019Water in the inner frame: Shoddy construction? (Shell construction)15
24.12.2019Windows are smaller than in the building application/work plan.40
02.12.2020Additional costs / surcharge Higher windows48
05.04.2021City villa window 1.26x1.45 visual error?10
25.11.2021Getting rid of moisture from the shell construction - how to ventilate and other topics18
29.11.2022Front view windows are suboptimal and need to be optimized90
27.11.2023Assessment of costs for the shell construction and total costs (plaster, screed)17
28.03.2024Offer for shell construction of a single-family house 170 sqm - Is the price market-appropriate?57
24.02.2025Construction Costs Shell/Turnkey Comparison39