Price increase despite fixed price!

  • Erstellt am 2022-04-07 13:45:36

Mikehausbau

2022-04-07 13:45:36
  • #1
We have also received a similar letter, we will first seek legal advice. Who else is in a similar situation? How much of an increase is possible? 10-20%? We could still get out of the contract, but the question is whether it is worth it.
 

tomtom79

2022-04-07 13:51:41
  • #2
Do you know the post?

https://www.hausbau-forum.de/threads/mehrpreise-von-10-trotz-pauschalpreisvertrag.43033/page-9#post-567721
 

Peter Pohlmann

2022-04-07 14:06:51
  • #3
What have I been writing here for weeks. Exactly that!

What do the construction companies want to do? The price doesn't even matter. It is impossible to get any material.
And as I said, I wouldn't calculate in percentages, but rather by how much the house construction doubles.

Still, first try to have a conversation. Try to find a solution together. Without a lawyer and all that crap.

The best solution in my eyes is simply to let the contract rest on both sides as it is. Wait and watch the market. And if the situation doesn't ease, then terminate it by mutual agreement.

Just imagine the following situation. The general contractor builds the shell, the carpenter the roof truss, and the roofer can't get any roof tiles anymore. What happens then? The whole shell building will get flooded. Who is helped then? You the least of all. Possibly irreversible damage occurs to the building. Then you sue, which certainly costs money, but also a lot of nerves. Not to mention the move-in date.

Now it doesn't have to be roof tiles, but underlay membrane, screws, nails, gutter hooks, or gutters. If one part is missing, it's game over.

The construction companies are now all pulling the emergency brake one after the other. What else are they supposed to do?
Welcome home!
 

WilderSueden

2022-04-07 14:08:26
  • #4
If you otherwise meet all the conditions, you can't just change the price guarantee. The construction period can possibly be extended by referring to force majeure; on that point, I am personally quite lenient.


Plan over it until the tiles arrive. Then not much water will get in either.
 

Peter Pohlmann

2022-04-07 14:15:02
  • #5
Exactly. You can make the tarp all the way down to the ground so that the windows and doors are also closed right away.
 

Mikehausbau

2022-04-07 14:25:34
  • #6
I am still confident, if things don’t work out with this company we will terminate our contract and award on our own initiative.
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
09.03.2015Received an offer from a builder: Cost of shell construction - experiences?26
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18

Oben