Sandra84
2022-10-29 19:52:32
- #1
Due to the following information
I "actually" only see the possibility that you perhaps let them do rework against another payment in an amount yet to be negotiated (--> compromise). Because the company seems basically capable of plastering well if some rooms are fine.
Were it always the same employees or were the last rooms perhaps plastered by trainees? I ask because you might then be able to use that as an argument.
A compromise would really be a solution, but the company says there is no possibility for rework. Everyone always looks quite helplessly at the wall.
It was always the same plasterers. But I must also say they plastered our detached house for 2.5 months. The entire house construction took almost three years. The construction company simply didn’t work at all for 5 months.