Planning empty conduits for satellite system and photovoltaic system

  • Erstellt am 2017-05-16 21:10:41

BenutzerPC

2017-05-17 13:21:15
  • #1
Just a naive question: Is the planning of the empty conduits for the work plan with the main contractor now decisive, or can I still spontaneously say during the shell construction: Electrician, can you install one or two empty conduits here for me? After all, it has not yet been clarified in the work plan where and how a satellite system will be installed. So, in short: What can I still arrange later, possibly directly with the craftsmen on site, or what do I already have to include now in the work planning, because it will no longer be possible afterward? According to the statements so far, the costs seem really exaggerated, I will also inquire about that again.
 

Mycraft

2017-05-17 13:50:05
  • #2
Clearly yes and no!
 

Alex85

2017-05-17 13:54:35
  • #3
I just read that 450€ are due per pipe, so 900€ for two.

One has to wonder if they are made of gold.

The material value is well below 100€.
 

Mycraft

2017-05-17 14:02:54
  • #4
Well, the question is what is included in the price. If you also count the mast, the grounding, the roof tile, and the labor... then it already adds up to a few euros... okay not 900 but certainly 300-500...
 

dohuli

2017-05-17 14:16:39
  • #5
Regarding planning: I don't know your contract and the flexibility of the general contractor/tradesman, but technically, you can of course also have empty conduits installed at a later date - provided there is enough space in the shaft.

We are currently building (the shell is finished) and as I have learned, I will do the electrical installation myself. For some things (including empty conduits), I will basically decide spontaneously while laying the cables what else will go where.
 

jaeger

2017-05-21 10:48:26
  • #6


But it’s not that simple. According to the standard, it looks like this: You must run a rigid Cu 16 mm² cable from the antenna to the grounding system preferably outside on the building. See page 12 in the following document (or section 11.3.2 of DIN EN 60728-11 / VDE 0855-1).

The deep earth electrode must be connected to the building’s grounding system.

Additionally, the antenna mast must be connected to the grounding busbar via a potential equalization conductor, for which you could use the 16 mm².
 

Similar topics
14.11.2011Shell construction still this year15
05.09.2015Cracks in masonry (shell construction)14
13.02.2014Mold on wood/ shell construction, is it possible to deduct the advance payment invoice?28
24.04.2015Buy tiles during shell construction24
09.03.2015Received an offer from a builder: Cost of shell construction - experiences?26
27.02.2015Purchase shell construction and complete it including financing15
11.02.2016Cost per cubic meter of built-up shell space14
07.05.2016Buying a shell construction - Experiences21
02.06.2016Conduit Costs - Network, SAT, Backup14
03.10.2016Single-family house, hillside location, basement half residential/useful area - expensive shell construction?15
20.04.2017Payment plan with 35% after the shell construction, okay?10
05.05.2017Rough construction flat-rate offer - forgotten necessary items11
06.09.2017Add a wind catch later to the shell construction17
07.10.2017From when must the shell construction be dry or sealed?16
18.12.2017Offers for single-family house shell construction and basement received - your assessment?21
31.01.2022Possible savings in self-performed structural work37
23.07.2020Empty conduits on the property - ideas? - It's not too late yet :)103
09.09.2019Are empty conduits and empty boxes in WU concrete dangerous?10
14.02.2021Empty conduits from the house to the garden / Tips10
04.07.2022Conduits for SAT and TK, mandatory or not in new construction?13

Oben