Hello everyone,
We have now almost completed the shell construction, except for these few remaining tasks:
1- 1 out of 4 exterior walls in the attic (the triangular wall under the roof truss).
2- Non-load-bearing interior walls.
3- The concrete staircase.
4- Incorrect door position and additional unplanned windows.
The construction company is now demanding payment for the "Richtfertigkeit des Rohbaus."
Is this really the right time to make this payment? The construction company claims that these remaining tasks are not relevant for this milestone, since the roof truss can now be erected (even though it has not yet been erected).
Their plan is to erect the roof truss and then complete the remaining masonry work.
Does anyone know if these are truly not relevant? Can we assume that the shell construction is now really finished?
Thank you very much
Best regards
We have now almost completed the shell construction, except for these few remaining tasks:
1- 1 out of 4 exterior walls in the attic (the triangular wall under the roof truss).
2- Non-load-bearing interior walls.
3- The concrete staircase.
4- Incorrect door position and additional unplanned windows.
The construction company is now demanding payment for the "Richtfertigkeit des Rohbaus."
Is this really the right time to make this payment? The construction company claims that these remaining tasks are not relevant for this milestone, since the roof truss can now be erected (even though it has not yet been erected).
Their plan is to erect the roof truss and then complete the remaining masonry work.
Does anyone know if these are truly not relevant? Can we assume that the shell construction is now really finished?
Thank you very much