C&C
2011-09-29 13:28:04
- #1
We are in negotiations with several general contractors. The loan agreement has already been signed. Part of the loan agreement is the following payment schedule:
30% after completion of the basement ceiling
25% after acceptance of the shell construction
25% after application of the interior plaster
20% after acceptance for use
However, our preferred partner requests 14 interim payments:
4% after completion of earthworks
6% after completion of the base slab
10% after completion of basement ceiling
10% after completion of the ground floor ceiling including backfilling of the working space
7% after erection of the roof truss including completion of masonry
7% after completion of roof covering including roofing work
7% after installation of windows including exterior windowsills and shutters
6% after completion of rough installation (electricity, heating, plumbing)
9% after completion of non-load-bearing walls
8% after completion of interior plaster
5% after completion of screed
8% after completion of electrical, heating, plumbing, interior stairs
8% after completion of exterior plaster
5% after handover of the house
The general contractor refuses to deviate from this. To me, this is a sign of insufficient liquidity, right? It can't be common practice, can it?
30% after completion of the basement ceiling
25% after acceptance of the shell construction
25% after application of the interior plaster
20% after acceptance for use
However, our preferred partner requests 14 interim payments:
4% after completion of earthworks
6% after completion of the base slab
10% after completion of basement ceiling
10% after completion of the ground floor ceiling including backfilling of the working space
7% after erection of the roof truss including completion of masonry
7% after completion of roof covering including roofing work
7% after installation of windows including exterior windowsills and shutters
6% after completion of rough installation (electricity, heating, plumbing)
9% after completion of non-load-bearing walls
8% after completion of interior plaster
5% after completion of screed
8% after completion of electrical, heating, plumbing, interior stairs
8% after completion of exterior plaster
5% after handover of the house
The general contractor refuses to deviate from this. To me, this is a sign of insufficient liquidity, right? It can't be common practice, can it?