Snuggles
2018-11-18 10:11:22
- #1
Hello everyone,
I am currently renovating an old warehouse (from the 80s) and setting up a small workshop + office for personal use. I am doing most of the work myself, except for essential things like utility connections for water / sewage / electricity. However, I do have some "knowledge."
Now I am facing the problem of the "new installation" of the power supply.
Background:
The old meter box was completely messed up, old, and overloaded [2 boxes approx. 200x600mm each || one with meter, one with circuit breakers]. There were already some failures (primary RCD kept tripping). So I had it disconnected and had a construction power distributor installed. I immediately commissioned the electrician to provide a quote for a new, large, future-proof cabinet.
Free-standing cabinet max. 2m high and max. 1.10m wide.
Should be able to handle 3x100A because of workshop / machines => Current transformer measurement is required.
Preliminary information was "Such a cabinet costs 2-3k€." *Phew* but what can you do.
Now an offer came in for just under 12k€ gross for a generously equipped current transformer cabinet (21xC32 rotary switches || 37xC16 rotary switches || 70x B16 single-pole 230V) with 3x160A current transformers including installation + connection, without final wiring of the outgoing feeders. Professionally assembled; brand "S+J."
The cabinet alone is supposed to cost 7k€ net wholesale. I don’t really know the electrician well, but he seems reasonable to me (I am an entrepreneur myself and have quite a good intuition by now... I dare to say. But I could be wrong!!).
Question:
Is something like this realistic? Or what alternatives are there for such a problem?
Reducing the circuit breakers, of course. Half of everything would suffice for me with a (later) subsequent sub-distribution...
Of course, I can google myself – and I already have. But then you only find some empty cabinets and mostly only 3x 63A. Above all, I am not sure if a smaller cabinet might also be sufficient.
Are there any well-founded opinions here from possibly professionals or people who have had something similar?
Thanks in advance + regards
Nicolai
PS: This whole thing is happening in the greater Karlsruhe area (BW). In case that is relevant…
I am currently renovating an old warehouse (from the 80s) and setting up a small workshop + office for personal use. I am doing most of the work myself, except for essential things like utility connections for water / sewage / electricity. However, I do have some "knowledge."
Now I am facing the problem of the "new installation" of the power supply.
Background:
The old meter box was completely messed up, old, and overloaded [2 boxes approx. 200x600mm each || one with meter, one with circuit breakers]. There were already some failures (primary RCD kept tripping). So I had it disconnected and had a construction power distributor installed. I immediately commissioned the electrician to provide a quote for a new, large, future-proof cabinet.
Free-standing cabinet max. 2m high and max. 1.10m wide.
Should be able to handle 3x100A because of workshop / machines => Current transformer measurement is required.
Preliminary information was "Such a cabinet costs 2-3k€." *Phew* but what can you do.
Now an offer came in for just under 12k€ gross for a generously equipped current transformer cabinet (21xC32 rotary switches || 37xC16 rotary switches || 70x B16 single-pole 230V) with 3x160A current transformers including installation + connection, without final wiring of the outgoing feeders. Professionally assembled; brand "S+J."
The cabinet alone is supposed to cost 7k€ net wholesale. I don’t really know the electrician well, but he seems reasonable to me (I am an entrepreneur myself and have quite a good intuition by now... I dare to say. But I could be wrong!!).
Question:
Is something like this realistic? Or what alternatives are there for such a problem?
Reducing the circuit breakers, of course. Half of everything would suffice for me with a (later) subsequent sub-distribution...
Of course, I can google myself – and I already have. But then you only find some empty cabinets and mostly only 3x 63A. Above all, I am not sure if a smaller cabinet might also be sufficient.
Are there any well-founded opinions here from possibly professionals or people who have had something similar?
Thanks in advance + regards
Nicolai
PS: This whole thing is happening in the greater Karlsruhe area (BW). In case that is relevant…