Long waiting time - building permit deadline

  • Erstellt am 2012-11-13 19:20:30

unser Haus

2012-11-13 19:20:30
  • #1
Is there a legal deadline for processing a building application? We submitted our building application in week 37. It was returned after 2 weeks because, for example, we had not indicated where the garbage bins would be or where green areas would later be on our property. After all the "errors" were corrected, it was sent back to the building authority. We are now in week 46 and have not received anything back yet.:mad:
 

Wastl

2012-11-14 08:38:42
  • #2
Every municipality/city ordinance has its own additional regulations. I believe in our area it is not longer than 3 months. Just call your building authority and ask what the status is.
 

Bauexperte

2012-11-14 09:14:29
  • #3
Hello,


If I understand you correctly, your building application has had an actual processing time of 5 - 6 weeks so far?

Most construction projects, especially residential buildings and garages, fall under the "simplified approval procedure." In this procedure, the review is only limited to compliance with the most important public-law regulations. Thus, only the planning law admissibility and essential building code requirements, such as parking spaces and setback areas, are examined. Approval for this is usually granted within 4-6 weeks; often unnoticed by the applicants if the architect has not marked a "notification field" on the building application.

Then there is the "regular approval procedure." This is the "most comprehensive" building permit procedure. It is carried out for the construction and modification of projects, facilities, and installations that are subject to special requirements. In this procedure, the authority examines compliance with all public-law building regulations. The issuance of a building permit in the case of a "regular approval procedure" can take up to 3 months or longer.

Best regards
 

unser Haus

2012-11-14 13:27:51
  • #4
Hello construction expert, thank you very much for the detailed response. The missing information was submitted to the building authority on 12.09. We are now in the 9th week. On Anlage 1/2 zu VV BauPrüf VO "Bauantrag" is checked, in the same line it says: "Project for which the simplified approval procedure is carried out". I have already called but without success. Best regards
 

JohnMockery

2012-11-19 16:53:20
  • #5
Hi,

I believe it is usually 3 months...by the way, on the topic that it can take longer...that can happen, but the authority has to justify why it is taking longer (complexity or something similar). Otherwise, if you don't hear anything after 3 months, your construction is approved as you submitted it...!!! That's how it was for a friend of mine...

Our preliminary building inquiry took almost exactly 3 months. 1 1/2 weeks before the deadline, the (positive) notice came that we can and may build on the property we have in sight :).

Jan
 

unser Haus

2012-11-19 17:05:20
  • #6
Hello, thank you very much for your reply. Do you also build in NRW? We are building in the heart of the Ruhr area!
With kind regards
 

Similar topics
29.10.2013Property reserved, construction financing plan, architect/building permit application21
10.05.2016Real estate transfer tax on land and house?12
09.04.2014Questions/neglected plot/meadow, determining construction measures44
05.10.2014Approval procedure for moving a house15
18.06.2015The plot must be developed. The general contractor says this is a priority!35
16.01.2017No building permit as long as the land is not developed?10
11.04.2017Building authority wants site inspection116
03.05.2017Is terrain modeling allowed on the property?20
07.06.2017Permeable traffic areas in the building application17
20.11.2020Wait with the building application because of the child construction allowance1354
11.05.2018Construction application costs only 40 euros due to exemption application?27
14.10.2018Building application - delay due to neighbor's lawsuit - experiences?21
27.03.2019A potential lawsuit against my construction project is looming! What now?85
26.02.2019Submit a building application before the land is paid for?11
30.11.2020Building Authority Problems - Purchased a Defective Plot56
05.08.2020Building a garden shed... Is a building permit necessary? Detours?17
30.01.2021The building authority rejects the building application because the house is planned too far back86
16.10.2021Floor plan single-family house, 2 full floors approx. 180 sqm, 600 sqm plot56
09.05.2022Building application due to parking spaces not approved. What can happen?30
10.03.2023Preliminary building approval positive, building application criticized position29

Oben