305er
2018-01-20 17:22:56
- #1
Hi, in our new build made of Ytong, the interior plaster was completed on 10.10.17.
On 23.10. the cement screed was installed with an additive of fast dryer. According to the screed installer, it can be covered after 14 days.
Now it is the end of January and in some rooms on the upper floor in certain spots it is still wet.
After Christmas, we placed a construction dryer for 10 days, which pulled about 1-1.5 liters per hour.
We ventilated regularly.
The heating program for the screed never ran properly, now it finally runs through.
It was thought that the walls are dry, but when the underfloor heating was reheated above 35 degrees, the same spots were wet again the next day.
One spot/corner also sounds hollow when knocking towards the dry area.
Is this still normal in those spots due to the enormous heat or do we have a moisture problem?
Our useless site manager says it is normal.
The very bad spots were before the construction dryer

On 23.10. the cement screed was installed with an additive of fast dryer. According to the screed installer, it can be covered after 14 days.
Now it is the end of January and in some rooms on the upper floor in certain spots it is still wet.
After Christmas, we placed a construction dryer for 10 days, which pulled about 1-1.5 liters per hour.
We ventilated regularly.
The heating program for the screed never ran properly, now it finally runs through.
It was thought that the walls are dry, but when the underfloor heating was reheated above 35 degrees, the same spots were wet again the next day.
One spot/corner also sounds hollow when knocking towards the dry area.
Is this still normal in those spots due to the enormous heat or do we have a moisture problem?
Our useless site manager says it is normal.
The very bad spots were before the construction dryer