Is follow-up financing common only with the architect?

  • Erstellt am 2017-01-27 13:54:19

Noelmaxim

2017-02-01 00:54:23
  • #1
The banker doesn’t just make this up, these are just the bank’s release criteria. I think this procedure is required by your bank for refinancing. I handle this with a civil engineer, where the costs for the statement 3 are in the lower three-digit range. You make the statement, stamp it, and that’s it; this is completely sufficient for most banks. If they refuse you the additional financing, you can terminate according to Baugesetzbuch§490, although whether this is worthwhile considering the prepayment penalties is another matter and must be calculated precisely. Possibly, the revocation instruction of your loan agreements is also faulty, and you could avoid the prepayment penalty by revoking the loan agreements even today. All of this would have to be examined.
 

Matt.K.

2017-02-04 11:41:08
  • #2


Yes, probably, unfortunately this was not communicated that way during the first appointment; back then they only said we should prepare a statement. Regarding whether a civil engineer is sufficient, I would now have to schedule another appointment and take time off.

I didn’t specifically ask about that, he only said architect, and I have now contacted several, but none of them wanted to sign my statement without checking the circumstances first.



Does that apply in general? I mean, I can understand it for a new build because otherwise the house wouldn’t be finished, but we bought a used house and have already been living in it for 3 years.



There’s not much pressure you can apply; we don’t even always have the same advisor, the Spa*da Bank’s structures aren’t set up that way. We already tried to have the last appointment with the same advisor, spent a long time online until I got that, but two days before the appointment it was changed to a different advisor.
 

Noelmaxim

2017-02-04 12:33:38
  • #3
I had written that this is regulated by law in the Building Code §490. Whether this is a sensible solution remains to be seen and calculated, especially because the current situation is also not a solution.
 

Similar topics
19.02.2015Development costs §127 Building Code12
22.09.2015Building Code - Developer Contract - Postponement of Contractual Handover Date14
15.10.2019Questions on the interpretation of § 34 Building Code59
14.04.2020Security deposit according to §650 of the Building Code20
06.05.2020Liberation § 31 Building Code: Roof pitch, roof shape, roof structures15
10.04.2021Delays with the general contractor, no deadline set according to § 650 Building Code65
21.08.2021§34 Building Code: Building Window and Garage21
29.12.2022Special right of termination according to § 489 Building Code - Refunds15

Oben