Is a high first installment common in a payment plan?

  • Erstellt am 2017-03-20 20:18:55

hugo78

2017-03-20 20:18:55
  • #1
Hello,

I am now also capable like many others here. I currently have a contract for a custom-built home to sign. I believe that as the client I am taking an unnecessarily high risk by signing it.

It concerns the following:
The first installment in the payment plan "Submission of the building application documents" is set at 7% of the total amount. At the same time, the contract states that I can withhold 5% of the contract sum if the contractor cannot provide me with a guarantee by the time the first installment is invoiced.

Practically, this probably means that I will only pay 2% for the first installment and keep the rest as security (I do not expect the guarantee to be provided).

The question for me is:
1. Is 7% for submitting the building documents reasonable and usual?
2. Some further installments are due at the start. They range between 5% and 10%. In a worst-case scenario (contractor insolvency), the withheld 5% from the first installment will never cover this. What do you think about this?

Thanks in advance for tips.
 

RobsonMKK

2017-03-20 20:34:18
  • #2
The question is always whether the contractor will agree to changes. If he does not, you have two options: 1. you find someone else or 2. you swallow the bitter pill and play by his rules
 

ypg

2017-03-20 22:41:35
  • #3
7% of what? The first installment refers to the production of all construction documents including the building application, house planning, structural analysis... Therefore, 7% does not have to be too high. Normally, about 5% is assumed. The construction company pays in advance. When invoicing the first installment, the building application should therefore have been submitted.

Best regards, Yvonne
 

hugo78

2017-03-21 06:17:14
  • #4
Thank you for the answers. The 7% refer to a total amount of €220,000 (house without land).
 

HilfeHilfe

2017-03-21 06:45:40
  • #5
Hello,

can you please post the complete payment plan in % here.

Then one can get a better picture.

Where you signed the contract, and cannot negotiate anything afterwards
 

hugo78

2017-03-21 19:52:58
  • #6
The payment schedule is as follows: 7% Submission of building application documents 5% Start of construction work 15% Completion of foundation slab 15% Completion of ceiling above ground floor 10% Completion of roof framework or carpentry work and ceiling above upper floor 10% Completion of rough heating installation and sanitary installation 10% Start of window installation 8% Completion of electrical installation 5% Start of interior plastering 5% Completion of screed 5% Start of tiling 5% Completion of agreed services and acceptance

What do you think?
 

Similar topics
12.03.2013What is the maximum rate for a net salary of 3,000 euros?24
26.09.2013What do you think of this payment plan?, Property appraisal18
22.07.2015Young family wants to buy a house, but does the installment fit?15
11.08.2015What can I realistically afford as a rate?51
14.12.2015Does my rate match the salary?38
08.12.2015Payment plan: paid too much at the beginning?11
03.09.2016Interest rate / rate - bank calculation16
28.11.2016Payment plan / Guarantee remaining amount Acceptance20
13.12.2016Realistic monthly rate59
17.07.2017Payment plan okay - 13% after the floor slab?21
30.06.2018Construction contract - Uncertainty regarding payment schedule33
08.10.2020Is the general contractor payment plan acceptable? Thanks for tips68
11.11.2018KFW negatively affects the rate. Still use it?11
05.06.2019GÜ insolvent - and now? (Payment plan etc.)23
07.05.2019Payment plan - unreliable? Your assessment11
02.02.2020Payment plan (Broker and Developer Regulation) and Developer's payment plan10
11.12.2020Payment plan and unpleasant feeling11
26.06.2021Position in the payment plan that is never fulfilled18
30.03.2022Terminate the contract with the general contractor "early"22

Oben