parallelsym
2023-02-13 08:56:42
- #1
Hello everyone,
First of all, thank you very much for your assessments/your advice!
We are in the building permit process (§52 State Building Code) for a single-family house in a municipality in Baden-Württemberg. The building plot is an old farm that we completely demolished in Q3 2022. The demolition application was approved without comment after about 1 month by the municipality and the district office. Since the building plot is a property in the old town center, there is no development plan.
At the beginning of September 2022, we submitted the building application to the municipality, which then approved it and forwarded it to the district office at the end of September. The deadline for feedback from the district office was set for 27.12.2022.
Minor inquiries from the district office could be resolved quickly in the following two months (mainly concerning the noise level of the integral air-water heat pump).
At the beginning of December, we received a letter stating that the agricultural department now also has to examine the emissions of the surrounding farmsteads. From this point on, there is no defined deadline for a decision on the building application anymore, as the building authority has not yet received all the documents.
At the end of January/beginning of February, we called various agencies to find out the following: In the Alb-Donau district, there is only one state employee who carries out inspections of the farmsteads for municipalities and private construction projects. This person now has two large orders from municipalities with about 300 inspections to be carried out and 8 inspections concerning our building project. Several remarks on this:
1) How is it possible that we only find out the extent of the delay in the decision on our building application through the most intensive efforts?
2) Why is there only one person who does this job?
3) How is it possible that there is no further processing of a matter for 2 months?
Background: Once the measurements are made, they still have to be calculated by another office. Then it can take up to another two months until a decision is made by the building authority. The responsible person now says it could take until the end of Q2 (end of June 2023) until he has made the measurements and forwarded them to the building authority. If you think about it, data about the farmsteads is surely collected elsewhere, so this certainly causes duplicate effort.
The 8 farmsteads partly consist of farmsteads that have not been cultivated for years, but agriculture and forestry have not yet been deregistered. Only one farmer has about 20 cattle at maybe 100 m air distance. I have never noticed any odor nuisance.
Quite a number of costs depend on the timing, which increase with further delay.
However, we are clueless how to accelerate something here or possibly report a process that is not legally proper.
If the building application is rejected, we wonder why we were allowed to demolish the old farm. Now 1,000 sqm stand empty in the middle of the village.
Primarily, we ask ourselves to what extent this whole process is reasonable for a private construction project.
First of all, thank you very much for your assessments/your advice!
We are in the building permit process (§52 State Building Code) for a single-family house in a municipality in Baden-Württemberg. The building plot is an old farm that we completely demolished in Q3 2022. The demolition application was approved without comment after about 1 month by the municipality and the district office. Since the building plot is a property in the old town center, there is no development plan.
At the beginning of September 2022, we submitted the building application to the municipality, which then approved it and forwarded it to the district office at the end of September. The deadline for feedback from the district office was set for 27.12.2022.
Minor inquiries from the district office could be resolved quickly in the following two months (mainly concerning the noise level of the integral air-water heat pump).
At the beginning of December, we received a letter stating that the agricultural department now also has to examine the emissions of the surrounding farmsteads. From this point on, there is no defined deadline for a decision on the building application anymore, as the building authority has not yet received all the documents.
At the end of January/beginning of February, we called various agencies to find out the following: In the Alb-Donau district, there is only one state employee who carries out inspections of the farmsteads for municipalities and private construction projects. This person now has two large orders from municipalities with about 300 inspections to be carried out and 8 inspections concerning our building project. Several remarks on this:
1) How is it possible that we only find out the extent of the delay in the decision on our building application through the most intensive efforts?
2) Why is there only one person who does this job?
3) How is it possible that there is no further processing of a matter for 2 months?
Background: Once the measurements are made, they still have to be calculated by another office. Then it can take up to another two months until a decision is made by the building authority. The responsible person now says it could take until the end of Q2 (end of June 2023) until he has made the measurements and forwarded them to the building authority. If you think about it, data about the farmsteads is surely collected elsewhere, so this certainly causes duplicate effort.
The 8 farmsteads partly consist of farmsteads that have not been cultivated for years, but agriculture and forestry have not yet been deregistered. Only one farmer has about 20 cattle at maybe 100 m air distance. I have never noticed any odor nuisance.
Quite a number of costs depend on the timing, which increase with further delay.
However, we are clueless how to accelerate something here or possibly report a process that is not legally proper.
If the building application is rejected, we wonder why we were allowed to demolish the old farm. Now 1,000 sqm stand empty in the middle of the village.
Primarily, we ask ourselves to what extent this whole process is reasonable for a private construction project.