How long does it approximately take from the start of planning until approval?

  • Erstellt am 2020-05-08 08:21:23

hampshire

2020-05-08 11:01:04
  • #1
Sixty-three.
Seriously:
You have the planning duration under control yourself.
You have the preparation of documents for the building application under control yourself.
Building permit varies between 2 and 10 weeks depending on the municipality. This can be easily inquired about.
 

vanny2705

2020-05-08 14:26:32
  • #2
Property purchased in October 2019, plans roughly created, offer obtained (We had already been to companies before and knew whom we would choose for the construction) in December to the architect. By the time everything for the building application was completed and clarified, it was February. Building application submitted and building permit received in April. Construction will start next week. Many building authorities need, for example, 6 months or more for the approval. Hope this helps you a little further.
 

nordbayer

2020-05-08 14:37:37
  • #3
It can also go faster with a lot of luck... Got the plot in June, planning until October because the architect from the general contractor was a bit slow and we kept wanting many changes to the floor plan ourselves, November signing, March start of construction, currently it looks like readiness for occupancy in August. Completely normal solid construction turnkey without a basement. Normal case? Rather not, judging by what you hear.
 

Lumpi_LE

2020-05-11 06:39:37
  • #4
Have you already read it?
 

M4rvin

2020-05-11 07:01:52
  • #5
With us (municipal property): 02/2018 Commitment for the plot 03/20 03/2018 Start of development 12/2018 Completion of the road 12/2018 Submission of documents (exempt from approval) 02/2019 Start of construction 09/2019 Move-in The plot was ready to go from January but could only start once the boundary stones had been set.
 

vanny2705

2020-05-11 07:15:55
  • #6


A question: in the end, did you do the flooring and painting yourselves or have it done?
We start construction Wednesday and are really hoping to move in before Christmas. We are doing flooring and painting ourselves.
 

Similar topics
15.02.2011Building permit application12
29.10.2013Property reserved, construction financing plan, architect/building permit application21
10.05.2016Real estate transfer tax on land and house?12
09.04.2014Questions/neglected plot/meadow, determining construction measures44
27.09.2018Cost of building permit in exemption procedure, new construction11
18.06.2015The plot must be developed. The general contractor says this is a priority!35
15.06.2015Garage - Building Application - Confusion36
28.11.2024Neighbor's lawsuit against approved building permit46
16.01.2017No building permit as long as the land is not developed?10
03.05.2017Is terrain modeling allowed on the property?20
07.06.2017Permeable traffic areas in the building application17
04.08.2017Building application or building notification15
22.01.2018Building on still foreign land - Waiting for building permit25
20.11.2020Wait with the building application because of the child construction allowance1354
11.05.2018Construction application costs only 40 euros due to exemption application?27
14.10.2018Building application - delay due to neighbor's lawsuit - experiences?21
04.01.2019Terrain modeling different from the building application - allowed? (NRW)36
26.02.2019Submit a building application before the land is paid for?11
25.11.2019Exemption procedure or building permit40
30.11.2020Building Authority Problems - Purchased a Defective Plot56

Oben