stefanh
2015-05-27 08:05:44
- #1
Hello everyone,
I received the final invoice yesterday from my heating contractor who installed the heating, sanitary system, and controlled residential ventilation for us.
The company was commissioned based on a complete offer that contains the following clause:
Our offer is a COMPLETE OFFER which guarantees that no additional costs will arise for you regarding our services.
However, the written commissioned offer differs from the final invoice in two items:
The additional costs amount to approximately €2000 net. Both items were neither verbally nor written commissioned.
When the additional buffer tank was silently installed in March, I called the company on the same day and asked what this new "device" was all of a sudden. I was then only told that this was now a requirement from the manufacturer and that the heating system only works this way. Of course, it costs more – at that point, I already verbally refused to pay for it. However, there was no response but only a written offer that I never signed.
Then, during the briefing on the heating system, I was told that we have a circulation line with a pump. Surprised, I told the installer that I knew nothing about it and had not commissioned it. He just said that he was giving the briefing and is not aware of the commissioning.
-> We have KFW funding (calculation was done without the circulation set – doesn’t this change the rating)?
My question now is – what chances do I have that I don’t have to pay for these two items, or what do you think about it and what options do I have?
Of course, I will contact the company, I just wanted to know beforehand how I should best react to such a situation. At first, I was quite disappointed that something was just imposed on us without asking us first.
Thank you and best regards
Stefan
I received the final invoice yesterday from my heating contractor who installed the heating, sanitary system, and controlled residential ventilation for us.
The company was commissioned based on a complete offer that contains the following clause:
Our offer is a COMPLETE OFFER which guarantees that no additional costs will arise for you regarding our services.
However, the written commissioned offer differs from the final invoice in two items:
[*]200-liter buffer tank for heating with insulation (and heating circuit efficiency circulator pump for individual room control).
[*]Circulation line with pump
The additional costs amount to approximately €2000 net. Both items were neither verbally nor written commissioned.
When the additional buffer tank was silently installed in March, I called the company on the same day and asked what this new "device" was all of a sudden. I was then only told that this was now a requirement from the manufacturer and that the heating system only works this way. Of course, it costs more – at that point, I already verbally refused to pay for it. However, there was no response but only a written offer that I never signed.
Then, during the briefing on the heating system, I was told that we have a circulation line with a pump. Surprised, I told the installer that I knew nothing about it and had not commissioned it. He just said that he was giving the briefing and is not aware of the commissioning.
-> We have KFW funding (calculation was done without the circulation set – doesn’t this change the rating)?
My question now is – what chances do I have that I don’t have to pay for these two items, or what do you think about it and what options do I have?
Of course, I will contact the company, I just wanted to know beforehand how I should best react to such a situation. At first, I was quite disappointed that something was just imposed on us without asking us first.
Thank you and best regards
Stefan