Hello everyone,

since we have one or the other financing request in the forum, I wanted to ask out of personal interest what a follow-up financing has cost you. I am well aware that a follow-up financing mostly results from an inaccurate cost estimate or forgotten items, but the specific position(s) and amount would be quite interesting.

Regards
Zaba
 

Evolith

2018-04-18 11:00:00
  • #2
Earth replacement: Estimated 20k, it cost 25k
Sewage pump + installation: 6k estimated, it ended up being 8.5k (I did not consider the installation)
Heating: We planned on district heating but couldn't find a craftsman who installs the system at fair prices, so we reverted to a heat pump, which cost 1000€ in planning expenses
Boundary staking for setting the garage: think it was 600€
Various smaller expenses that added up. In total, this resulted in an additional financing of 15k€
 

halmi

2018-04-18 11:06:21
  • #3
How did you then realize the follow-up financing and under what conditions compared to the original financing?
 

Evolith

2018-04-18 11:13:50
  • #4


We did that through a small loan. At about 3.5% interest. It is now being repaid within 4 years (a little over 3 years remaining) and can also be paid off faster through special repayments. So yes, follow-up financing really hurts. The monthly rate is as high as for my two KfW loans.
 

HilfeHilfe

2018-04-18 11:19:29
  • #5


worst case is always.

from 25k you usually get a construction loan at better conditions than a small loan.

A follow-up financing can also result in your original construction financing being adjusted in terms (because of the lien if you have spent equity elsewhere).

A follow-up financing is always at higher conditions and you are in a bad starting position.

Building too cheaply is always the highest risk
 

Lumpi_LE

2018-04-18 11:22:55
  • #6
1) Planned own work that we simply didn’t have the energy to do in the end (e.g. painting) 2) "We'll do the exterior landscaping later..." Now it just needs to be finished... 3) Car broke down during the construction period, kitchen significantly more expensive than estimated, furniture, lamps, decorations... that costs money and wasn’t taken into account...
 

Similar topics
09.04.2013Construction financing in Berlin33
29.11.2013Is construction financing possible for a sauna?14
30.09.2014Construction financing in cash - which account?14
01.04.2016Construction financing | Is the procedure good? Your opinion and tips160
04.04.2015Separate construction financing?10
14.08.2015Construction financing... realistic and sensible?19
27.08.2015Which construction financing is suitable for us?10
17.12.2015Kfw funding 2016 - How to set up construction financing?10
18.03.2016Debt restructuring in construction financing36
08.09.2016Construction financing is available11
10.01.2017Construction financing without equity capital, but with other liabilities36
16.01.2018Construction financing - is it possible to reduce the interest rate?30
11.06.2018Is additional financing possible or necessary?17
26.07.2018Additional financing for real estate transfer tax47
18.12.2019Construction financing despite a very bad Schufa score60
25.01.2021Supplementary funding - WohnRiester27
26.10.2022Costs are rising sharply - is additional financing currently possible?39

Oben