I have received an offer (attachment) from my general contractor for the earthworks on the property and would kindly ask you to briefly evaluate it according to the following two points:

- Is the price reasonable as it is, or is it worth obtaining additional offers for the work?

- Does the offer cover the most important (costliest) work, or has something been forgotten?

The removal and disposal of the topsoil was deliberately not included in the offer, as we want to use it on the property (2100 sqm) to level or shape it. Are the approximately 200 cubic meters too much to be distributed meaningfully on the property, or is that suitable? Can the excavation be spread around the site using a mini excavator by oneself? The terrain is somewhat uneven and slightly sloping (about 1 meter from north to south if I understand the measurement correctly). I have also attached a map of the property with the surveyor’s elevation measurements.



Thank you very much for your assessments.
 

Grym

2016-09-16 21:41:19
  • #2
What is being done? Soil replacement?
 

Horst123

2016-09-16 21:48:42
  • #3
The offer is attached to the post or did that not work? It is displayed for me....
 

Grym

2016-09-16 21:51:37
  • #4
Yes, I'm involved. It was just a question of understanding. 220cbm fill material? I was told that about 300cbm are excavated for a basement construction, so that means that already 2/3 of the basement is being backfilled!?
 

Horst123

2016-09-16 21:55:37
  • #5
Ah, now I understand. No basement single-family house with a 9.1x12.6m footprint and floor slab. Are any other details needed for an assessment?
 

Grym

2016-09-16 22:11:17
  • #6
Yes, as I said, no basement but backfill material = 220 cbm.

The offer is now in addition to what is stated in your house contract? So in your house contract, topsoil stripping and excavation of 30 cm, etc. were specified, and these are now additional foundation costs?
 

Similar topics
28.01.2010House with or without a basement? - Experiences20
18.08.2013Massive house with basement. Is our budget enough?11
14.08.2012Build a home? Land in prospect19
25.03.2012Land now - house construction next year23
09.06.2013Costs of earthworks without basement15
19.04.2013Budget for the construction of a single-family house with a WU concrete basement27
27.05.2013Cost estimation: prefabricated house, basement, carport, single garage10
22.08.2013Buying land for a house, please advise!46
04.03.2015Budget plot and building with basement21
30.09.2019200m2 single-family house for 4-5 people without a basement on a narrow plot67
30.09.2019Floor plan optimization of a single-family house with a basement on a small plot178
27.06.2020Level the basement or the plot?43
27.01.2020Building a single-family house with/without a basement on a small plot65
28.07.2020Single-family house 160m2 with basement, 500m2 plot108
09.10.2020Single-family house 220 sqm with basement on 700 sqm plot41
19.10.2020Street about 50cm above the property - backfill or basement24
28.11.2020Expensive plot + single-family house 155 sqm + cellar KFW40+, financeable?60
04.03.2022Property development - basement yes or no?75
09.09.2024Floor plan design: Single-family house with basement; 560 sqm plot65
18.04.2024Floor plan design: Single-family house; with basement; 800 sqm plot10

Oben