FrauGese
2012-06-16 19:17:30
- #1
Hello everyone,
I have been a member of this forum since today and am now writing my first topic, exciting
We bought a plot of land that is almost 700 m² in size.
In order for the bungalow (125 m²) to be built on it, the following earthworks must be carried out (according to geologists after soil samples):
At the front left, the soil must be dug out about 3 m and then replaced layer by layer + compacted. In the middle/back left, 1.25 m of topsoil must be removed and filled with gravel + compacted.
Then the plot must be filled with 50 cm of load-bearing soil so that we are above street level...
And then everything should be prepared so that the base is ready...
Can anyone tell me roughly how much this will cost if you hire a company?
We are already waiting for an offer, but have no idea/comparisons...
Best regards FrauGese
I have been a member of this forum since today and am now writing my first topic, exciting
We bought a plot of land that is almost 700 m² in size.
In order for the bungalow (125 m²) to be built on it, the following earthworks must be carried out (according to geologists after soil samples):
At the front left, the soil must be dug out about 3 m and then replaced layer by layer + compacted. In the middle/back left, 1.25 m of topsoil must be removed and filled with gravel + compacted.
Then the plot must be filled with 50 cm of load-bearing soil so that we are above street level...
And then everything should be prepared so that the base is ready...
Can anyone tell me roughly how much this will cost if you hire a company?
We are already waiting for an offer, but have no idea/comparisons...
Best regards FrauGese