so first of all, thank you for your answers, that already calmed me down a bit before today's conversation with the architect. so here is the situation: the window construction company admitted the mistake and made me 2 proposals. either leave it as is and get half of the costs waived (the architect says his gut feeling tells him that if you negotiate properly, they would waive (almost) everything) or they replace it completely, remodeling really isn’t possible. then they would also have to pay the additional costs that would still be incurred for the other trades, the screed can’t be filled up to the sliding door now, the parquet layer has to come again, etc. of course, the company would like to leave the door in as it is now, I don’t want that. I communicated that now. luckily the company doesn’t seem to be stubborn about it, that reassures me a lot. the delay will now be about 4 weeks.