Delivery and Payment of Prefabricated House - What Is Accepted?

  • Erstellt am 2018-12-04 13:16:03

Frank Hartung

2018-12-07 18:05:57
  • #1
If tiling work, exterior plastering, and sanitary fixtures are still outstanding, there can be no final acceptance and certainly no final payment. For a final acceptance, all contractually owed services must have been rendered. Is this a contract from 2017 or already one according to current construction law?
 

Skyfire

2018-12-07 19:01:14
  • #2
It is a current contract from 2018
 

Frank Hartung

2018-12-07 19:52:08
  • #3
How high is the agreed final installment there, ?
 

Skyfire

2018-12-08 01:22:24
  • #4
15% of the house price is agreed as the final installment
 

Frank Hartung

2018-12-08 09:55:43
  • #5
then the contract is apparently okay so far. Be sure to also proceed according to the contract. If a contractor insists on acceptance in order to receive the payment installment, all alarm bells should always ring!
 

Skyfire

2018-12-14 14:23:50
  • #6
The problem is resolved and the contract will be followed. So no premature acceptance
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
09.05.2021Price adjustment clause in the contract with the general contractor18
30.03.2022Terminate the contract with the general contractor "early"22
27.01.2024House purchase through agent, now contract terminated18

Oben