11ant
2021-11-27 13:02:18
- #1
One might also come up with the idea to carry out the sample selection already during the planning phase. Which tiles and interior doors one wants has nothing to do with room layout and roof pitch, so logically, they don't have to wait for each other.What currently leads to longer waiting times at Streif Haus are the sample selections. It can take quite a few months (after the building permit) to get an appointment for the sample selection. [...] Planning with the architect, then building application (which varies significantly depending on the region), then sample selection, approval, and then production