Package price,
demolition of garage, 2 old sheds asbestos roof, trench, pipes, cables, construction road, leveling, paving, terrace, turf in total approx. 45 T€
 

hansi1234

2020-06-28 13:25:57
  • #2


Can someone tell me when I have to provide the own work? Does that happen when digging for the house?

I’m currently considering whether the crew that digs out the basement can do it, or maybe a landscaper?! Or I myself with a mini excavator.
 

Nida35a

2020-06-28 13:35:00
  • #3
Statement from our construction company: We will start when the construction road is in place because the path for excavators, excavation, fill sand, concrete pump, construction vehicles, deliveries of stones, roof tiles, roof truss all goes to the construction site, nothing will be carried 60m in from the road Nida
 

danixf

2020-06-28 13:37:00
  • #4
It entirely depends on the conditions of your property. If you only have a 3m driveway that must be used by all construction vehicles, then that's not practical. If you have enough space, I would call your utility provider by phone and ask accordingly. But don't forget that the trench also has to be closed up again, and ideally, that shouldn't happen only when the landscaper arrives. It only takes one stone to fall awkwardly into the trench and damage a pipe—or in the worst case, even a cable. Although you can temporarily fix that with a shovel at first. If you hand the excavator driver 50€, he'll probably agree to dig a trench for an hour... Everything is cheaper than directly through the utility provider. Call them first. Everything else will then explain itself.
 

Nida35a

2020-06-28 13:43:41
  • #5
Offer from the civil engineer of the construction company was demolition and construction road 22 K€, paved path 30 K€, rectangle 6cm, 70m x 2.8m, after the initial shock we took care of it ourselves and went with EL on the above-mentioned package Nida
 

Nida35a

2020-06-28 13:53:07
  • #6
Our pipes and empty conduits were in place and the construction road was closed when the construction company started. The trench extended to the utility room, the construction road up to 2m before the future floor slab. The pipes were closed and electricity was connected at the construction power box Nida
 

Similar topics
26.10.2015Hang securing > overcoming 1.30 m / house in a "ditch"25
04.09.2015Electricity connection to supplier Süwag10
20.09.2018Construction of lines on the property - experiences?14
18.09.2019The price from the gardener is justified - can something be omitted?56
13.08.2020Assessment of pathway plot with important municipal lines10
12.10.2020Main Pipeline Plan - Wastewater Drainage and Elevation Planning49
29.01.2021Gardener only mentions net prices96
25.03.2021Leading pipes from the house into the garage14
11.04.2021Crossing lines of various supply lines12
24.07.2021Disconnection of pipes before demolition -> Costs/Experience?15
13.11.2021Requirements for ancillary apartment, wiring, meters, etc.13
25.09.2023The supplier has incorrect meter numbers in the system - what to do?42

Oben