Hmm. I think we're talking past each other.
I'll try with a sketch. As you can see, the construction road is actually a bit short for the back construction area. However, the site manager can live with that. But of course, that also means that the construction road must be driven on all the way to the end. We can't block off any more.
The questions now are,
- can the cistern be damaged? How likely is that?
- can the construction road be damaged (sink) if the cistern stays?
- is it enough to simply fill the cistern with water to sufficiently prevent both?
- isn't there an even greater risk for the construction road if you now dig out, remove, and refill on your own?
Thanks and regards
Tolentino