So our construction started on 30.01.17 with pouring the foundation slab. By the end of March, doors and windows were installed. In between, we had a 3-day construction stop because the thermometer showed below -5°C....
A lot of speculation and generalities. The fact that construction can take place under various climatic conditions is proven worldwide by practice. I would say: - Ask the processing guidelines of the respective manufacturers (of course, you have to know which building materials are being used). - Check the contract for work to see if there is a completion date.
A lot of speculation and generalities. That construction can take place under various climatic conditions is proven by practice worldwide. I would say:
- Check the processing guidelines of the respective manufacturers (of course, you need to know which building materials are being used).
- Look in the contract to see if there is a completion date.
Regarding point 1: I received the datasheet, which states that up to >5°C no additional measures are required.
Regarding point 2: The occupancy date is 10 months after completion of the foundation slab. Bad weather, strikes, etc. would extend the deadline.